Basin Jetty Repair - The Basin Road

The Shoalhaven was declared a Natural Disaster Area 5 March 2022 after an East Coast Low and subsequent rain events. This had a major impact on our communities with severe damages to infrastructure. The Basin Road Jetty was severely impacted, Council has scheduled repair works.

Long distance view of damaged jetty and water

The latest

Works will be carried out by councils' contractor GPM Marine Construction and includes:

- disposal of existing timber structure
- rehabilitation of existing concrete footings
- install of FRP structural member and mesh decking
- solar light, water, fishing table

Select image to view jetty design

About the project

Media release

Basin jetty repairs begin in spring following tender award 

Image gallery

Damaged Basin Road jetty scheduled for reconstruction works 

2024 Works history

3/10/2024 - Contractor GPM Marine will start construction in conjunction with works on Island Point Road jetty program which starts on Monday 14 October 2024.

15/8/2024 - Jetty renewal is planned to start September 2024 with an expected completion by early 2025. The works have been awarded to GPM Marine Construction

13/8/2024 - The last update for this project is current. Further information will be provided as it becomes available. Subscribe to this page for updates. 

22/7/2024 - The construction contract has been awarded. Works are planned to start in September 2024 with a target completion date anticipated for early 2025.

27/6/2024 - The last update for this project is still current. Further updates will be provided as new information becomes available. Subscribe to this page for updates. 

4/6/2024 - The last update for this project is still current. Further updates will be provided as new information becomes available.

09/05/2024 - The tender for the repair works has now closed with tender submissions currently under review.

12/04/2024 - The tender for the repair works has been released.

15/02/2024 - Council has received funding approval to undertake repairs to the Basin Road Jetty. Tender documents are currently being prepared.

 

2023 Works history

Damaged Basin Road Jetty following severe weather events 2022

02/11/2023 - Detailed design for replacement of the jetty is complete and Council will be issuing a tender for the work. It is expected works will commence in the new year following the tender process.

02/11/2023 - Detailed design for replacement of the jetty is complete and Council will be issuing a tender for the work. It is expected works will commence in the new year following the tender process.

28/09/2023 - Council has received funding approval from Natural Disaster Recovery Arrangements and the NSW Department of Primary Industries (NSW DPI). Detailed design and environmental approvals are near completion.

13/07/2023 - Funding for repair works has been endorsed by the Public Works Authority and Council is currently working with them to clarify design and cost estimates.

08/09/2023 - Council has received funding approval from Natural Disaster Recovery Arrangements and the NSW DPI. Detailed design and environmental approvals are nearing completion. The works will be coordinated with assistance from NSW Public Works.

07/06/2023 - Council has obtained cost estimates and concept designs for both "like-for-like" and betterment options relating to the jetty and are liaising with funding authorities to obtain grants to undertake the works.