Bream Beach Water Main and Naval Parade Sewer Main Relocations

Shoalhaven Water has developed a list of mains which have been identified as susceptible to breakage and/or reaching end of life.
Construction of the sewer main on Naval Parade has commenced - residents may experience some detours due to road closures.

Bream Beach (29).png

The latest

  • The water main has been commissioned.

  • The sewer construction main on Naval Parade is approximately 80% completed.

  • Residents may experience some detours due to road closures.
  • About the project

    In 2020 Shoalhaven Water identified a list of water and sewer mains that were at risk of breaking, or reaching the end of their lifespan.

    Shoalhaven Water engaged a consultant to undertake the required design services, with subsequent construction works to be delivered. For more information about the identified list of mains, please refer to the parent project, Design Services – Mains Program.

    Progress so far

    • detailed designs completed in 2023
    • Bream Beach water main - Review of Environmental Factors (REF) publicly exhibited in July 2023
    • Naval Parade sewer main – REF publicly exhibited in October 2023
    • construction of Bream Beach water main commenced at Fisher Street in June 2023 and construction is about 95% complete
    • construction of Naval Parade sewer main commenced in July 2024

    About the packages of works

    Shoalhaven water has commenced construction for the water main at Bream Beach and the sewer main at Naval Parade. Read more about these packages of works below.

    Bream Beach water main

    The water main running through Bream Beach is considered critical according to the Council’s asset management system as it’s the sole main supplying water to Wrights Beach. However, the existing service faces growing issues due to its age, the type of pipe used (white PVC), and its current location beneath a caravan park.

    Shoalhaven Water has completed a detailed design for relocating this water main. The goal is to upgrade it, enhance its usefulness, and reduce the risk of ongoing breakages.

    Naval Parade sewer main

    The sewer rising main from SPS 22 in Wrights Beach currently discharges into the existing sewer gravity main along the St Georges Basin foreshore.

    However, this sewer main is affected by changing water levels within the basin. As part of the associated Coastal Management Plan, there’s a proposal to relocate the sewer main to Naval Parade Road.This relocation aims to prevent future discharges into St Georges Basin

    Photo gallery

    Jump to subscribe