Cambewarra Dam Decommissioning

This project is located in Cambewarra at the end of Tannery Road. Cambewarra Dam is a composite concrete gravity and earth fill embankment dam, owned and maintained by Council that is proposed to be decommissioned.

Callala Beach (39).png

The latest

Work to remove the Concrete Dam Structure is nearing completion. Removal of the earthen embankment surrounding the reservoir and earthworks to fill the reservoir have commenced.

Work is scheduled for completion July 2025.

About the project

The Cambewarra Dam, which is over 100 years old, used to serve as a water storage facility for the Nowra township. However, it has been disused for the last 40 years and no longer fulfills any useful purpose.

In 2012, Council hired a consultant to conduct an assessment and evaluate the options for the future of Cambewarra Dam, which resulted in the decision to decommission it. This process involves removing the concrete wall and backfilling the dam site using the embankments.

Progress so far

  • Detailed Design completed
  • Tender phase is complete
  • Site work has commenced
Jump to subscribe
Tagged as: