March 2024 Update - Preliminary works in progress. Site establishment and tree clearing to commence towards the end of March 2024.
February 2024 Update - Drainage works to commence on 26 February 2024.
January 2024 Update - Watermain relocation works are complete. Drainage works to commence from Sandra Street in February 2024.
November 2023 Update - Pipes are on site. Budget has been confirmed - only stage 1 will be completed in FY 2023-24. Shoalhaven Water will be undertaking the necessary watermain relocation towards the end of November. Drainage installation to commence early in 2024.
September 2023 Update - Pipes will be delivered to the end of Sandra Street on Monday 25th September. Budget for the works is still pending confirmation.
August 2023 Update - Project budget will be confirmed in September but is unlikely to allow completion of both stages at once. Council's intention is to deliver stage 1 of the works (Sandra to Esme Street) late in 2023.