Far North Collector Road Network

The Far North Collector (Bannada Way) will link Illaroo Road (near the western end of West Cambewarra Road, Bangalee to Moss Vale Road (at Bells Lane) in Cambewarra.

fncr feb 2023 low res.jpg
  • Project StatusConstruction
  • Where Banada Way, Badagarang 2540
  • Project value$35,160,000
  • Project scheduleConstruction period June 2020 to July 2024
  • Public access
    open
  • Last reviewed 05 August 2024

The latest

Bannada Way will officially open to traffic on Tuesday 6 August 2024.
Opening to traffic is expected to occur prior to 12pm following a final inspection by the project team.
Minor ancillary works will continue until September 2024 such as landscaping and site cleaning. Motorist may experience minor disruptions during these times.

About the project

Background

The project is an integral component of the overarching “Preferred Road Network” adopted with the Nowra Bomaderry Structure Plan.

The Far North Collector Road project has been divided into 4 stages:

  • Stage 1: Illaroo Road Roundabout (completed in March 2021)
  • Stage 2: Moss Vale Road intersection with Far North Collector Road (forecast completion June 2024)
  • Stage 3: The connection between Illaroo Road and Moss Vale Road with a connection to Taylors Lane (Completed December 2023, not open to traffic)
  • Stage 4: Connection to Taylors Lane

The construction contract for Stages 2 and 3 was awarded in March 2022 to Cleary Bros with construction of stage 3 commencing in May 2022 with Stage 2 commencing in November 2022. Stage 3 is due for completion by the end of 2023, and Stage 2 being the Moss Vale road roundabout is due for completion in Q2 2024.The road willbe opened following the completion of the roundabout in July 2024.

Naming of the Far North Collector has progressed with the proposed name 'Bannada Way' being endorsed by the Nowra Local Aboriginal Land Council, and Council. The word Bannada is southern Dharrawal for the Bomaderry Creek or Running Water.

Council has endorsed a new alignment of Taylor's lane which coincides with the proposed adjacent development, this looks to retain the trees on the current Taylor's lane alignment. This connection will not be constructed as part of these works.

This project is 100 percent Federally funded.

Upcoming works

In the coming weeks, the southern lane of Moss Vale road will be reconstructed and the roundabout construction will commence. Other notable items will be the installation of street lighting and the energisation works associated. Taylor's lane will be permanently closed to Moss Vale Road as required by TfNSW approvals. Access to the eastern end of Taylors Lane will be through Bannada Way.

Photo gallery

History

April 2023 - Works commenced on a new roundabout that will form the connection for the FNCR network to Moss Vale Road. Construction of the new roundabout will take approximately 6 months, weather permitting.

Feb 2023 - Works are progressing well and Cleary Bros will soon start work to construct the roundabout on Moss Vale Road (intersection of Bells Lane and Moss Vale Road). Barriers and reduced speed limits will be in place.

December 2022 - From mid-December, the bridge beams are in place over Bomaderry Creek which spans 110 metres and major earthworks are complete. Stormwater components are being installed. The remaining three bridges will be assembled over the coming month. Preparation works are currently underway for the Moss Vale Road roundabout.

September 2022 -  The foundations for all four new bridges are in place, including the 108 m bridge over Bomaderry Creek and floodplain. Concrete bored piles have been installed into high strength rock to create the support for the new structures.