- Project StatusIn Progress
- Where
Berry Street, Vincentia 2540
- Last reviewed
05 August 2024
The latest
Construction has commenced on this project. Installation of pipework on Berry Street and McNamara Street is in progress. Construction work is not expected to interrupt supply services to residents.
About the project
Shoalhaven Water, as part of their asset management practices, has decided to upgrade and replace the sewer rising main, gravity main, and pump station in Montague Street, McNamara Street, and Berry Street Vincentia.
Detailed designs have been completed for the upgrades to the rising main and gravity main at Sewer Pumping Station (SPS) 7 on Montague Street.
These upgrades are necessary to handle increased wastewater flows, improve efficiency, and reduce the risk of wastewater overflows into the environment. A Review of Environmental Factors (REF) report was publicly exhibited in November 2023.
Progress so far
- Review of Environmental Factors (REF) prepared in March 2023
- detailed designs completed in August 2023:
- Review of Environmental Factors completed, publicly exhibited and endorsed in November 2023
- construction commenced in May 2024
- installation of pipework on Berry Street and McNamara Street has commenced