20/02/2024 - Shoulder seal to occur early next week weather permitting.
17/01/2024 - Bridge complete and in use. Remaining items to be completed over the next couple of weeks.
21/12/2023 - The shared user path bridge is now in use. Minor works are remaining.
20/11/2023 - Screw piling complete. Work on abutments and path continuing.
01/11/2023 - Drainage works are complete. Screw piling and earthworks continuing.
03/10/2023 - Tree removal is complete. Earthworks to commence from Monday 9th October.
26/09/2023 - Site has been established. Additional tree clearing to take place on Thursday 28th September. Earthworks to commence after Monday 2nd October public holiday.
September 2023 Update - The final design is being reviewed. Preliminary construction activities to commence early October 2023.
August 2023 Update - The contract has been awarded. The contractor will commence with the final design and pre-site works requirements.
June 2023 Update - Tender evaluation has been completed and is progressing through the internal approval process.
May 2023 Update - Tender submissions are being evaluated.
April 2023 Update - Design & Construct tender is currently live - submissions due late May 2023.
March 2023 Update - Tree clearing and geotechnical investigation are complete. Final concept package is due early April 2023. Project will be tendered as a Design & Construct contract soon after.
February 2023 Update - Tree clearing will take place on Thursday the 16th and Friday the 17th of February as an early works package. This will allow a comprehensive geotechnical investigation to take place and the concept design to be finalised.