17/10/2024 - Asphalt works and installation of the shelter have been programmed for early November 2024.
02/10/2024 - Works are nearing completion.
27/8/2024 - Construction of the rock revetment is nearing completion. Works will now focus on the construction of the fish cleaning facilities.
14/08/2024 - Construction of the rock revetment has commenced. Works included the removal of the fish cleaning tables, damaged concrete slab and part of the existing collapsed timber retaining wall.
01/08/2024 - Preliminary works have commenced. Works will include the establishment of the site/compound area and installation of erosion and sediment control devices.
June 2024 - Council has obtained Natural Disaster Recovery funding to complete the revetment wall and fish cleaning table replacement. Works are expected to commence in July 2024 weather permitting.