Levee repair site DM00947
03/10/2024 - Works to repair flood damage on Comerong Island levee are complete.
16/8/2024 - Additional damage areas have been approved for repair. Works are continuing and are expected to be completed in September 2024.
Below: Levee repair works are under construction and in progress 4 July 2024


27/6/2024 - The last update for this project is current. Further updates will be provided as new information becomes available.
22/05/24 - The tender for repair works on Comerong Island has been awarded. Works are anticipated to start in June 2024 with completion in August 2024, weather permitting.
20/5/2024 - The last update is still the most current for this repair work. Further updates will be provided as new information becomes available.
24/04/24 - The tender has closed with a report to go to Council meeting 6 May 2024, to accept the recommended tenderer. Works are anticipated to start from either late May or early June 2024.
01/02/2024 - Levee repair works will be tendered in February. Construction dates will be advised after that.
27/10/2023 - Design and investigation works are currently out for tender and due to close 9 November 2023. Following a review of tender submissions the program of works will be announced.