- Project StatusConstruction
- Where
39 Timbs Street, Ulladulla 2539
- Estimated completion date22 March 2024
- Last reviewed
24 July 2024
The latest
04/04/2024 - Project is complete.
About the project
The north-eastern bank of Millards Creek in front of 39 and 41 Timbs St, Ulladulla deteriorated significantly during the storm events in 2022.
The proposed restoration works involve minor vegetation clearing, excavation, placement of rock rip rap to the creek bed and batter and revegetation.
An extensive Review of Environmental Factors has been undertaken to assess all potential impacts on the environment that the proposed project may present. The Review of Environmental Factors - Millards Creek - Bank Restoration Works is published on this web page for public viewing. The REF is being published, for information only, in accordance with Section 171 (4) (of the EP&A Regulation).
Estimated Timeline
- Project tendering: September 2023
- Construction commencement: November 2023
- Construction completion: March 2024
History
- 06/03/2024 - Rock placement in creek bed and batter is complete. Placement of fill and geocell on batter is in progress.
- 20/02/2024 - Rock placement in creek bed and batter is nearing completion. Earthworks behind rock batter are commencing.
- 17/01/2024 - Works have commenced.
- December 2023 Update - The contract for the works has been awarded. Contractor pre-works documentation and Fisheries permit is in progress. Works to commence mid-January and are expected to be complete by the end of February 2024.
- November 2023 Update - Tenders have been evaluated and the contract should be awarded in the next few weeks.
- Council is currently tendering these works with construction to take place later in 2023 pending a favorable outcome from the tender process.