Murramarang Road Shared User Path - Section 2

Construction of a 2.0m wide Shared User Path (SUP) along the eastern side of Murramarang Rd. The proposed path will extend the existing SUP (which currently terminates at the Racecourse Beach Holiday Park) for 840m until the Shelly Beach access carpark.

Murramarang-Stage-2-completed-path-2.jpg

The latest

16/04/2025 - This section of the project is complete pending installation of the handrail at the culverts.

About the project

Section 2 - Tasman Holiday Parks Racecourse Beach to Shelly Beach Access Carpark

Council has gained NSW Government funding to complete this section of path as part of the election commitment to support active transport in the Shoalhaven region.

History

  • 27/02/2025 - Construction is continuing on the final section of path near Shelly Beach carpark.
  • January 2024 Update - Construction is continuing from the northern end working south.
  • December 2024 Update - Construction is continuing from the northern end working south.
  • November 2024 Update - Construction has commenced with site establishment, survey set-out and service locating. Tree clearing and grubbing scheduled for 25/11/24.
  • October 2024 Update - Construction to commence early November.
  • September 2024 Update - The construction contract has been awarded.
  • July 2024 Update - Construction tenders are due in by 15 August 2024.
  • June 2024 Update - Tender documents are being prepared. Tender is expected to be released in July 2024.

     