November 2024 Update - Jirgens Civil have been awarded the contract to construct the paddlecraft launching facility. Procurement of materials is in progress. Construction is expected to commence in February/March 2025 provided that Lake Tabourie is open to the ocean at the time.
July 2024 Update - The Short Street Paddlecraft Facility has been confirmed as a project for the 2024-25 financial year. The construction contract will be tendered in August 2024.
November 2023 Update - Sufficient budget is not available to allow award of the contract. The project is being deferred.
01/11/2023 - Council is continuing to seek funding options internally to allow award of the contract.
20/09/2023 - Council is continuing to seek funding options internally to allow award of the contract.
01/08/2023 - Council is continuing to seek funding options internally to allow award of the contract.
28/06/2023 - RFQ submissions have been evaluated and the preferred contractor is known. Council is seeking additional funding internally in order to be able to award the contract.
25/05/2023 - RFQ submissions are being evaluated.
21/04/2023 - Construction quotations have been requested and are due to be received by Tuesday 16th of May.
21/03/2023 - The final design has been received and an RFQ for construction is being created.
03/03/2023 - The concept design has been agreed with the TLRRA and is in the process of being finalized as construction drawings by the designer.