3/10/2024 - Procurement for the jetty components has been completed. Final environmental assessments are being conducted prior to start of works. This project is on track for completion as planned, early 2025. Find key features of the replacement jetty and the design plan under 'The latest'.
21/8/2024 - Works have been awarded to GPM Marine Construction and are planned to start in September 2024 with the target completion date early 2025.
13/8/2024 - The last update for this project is current. Further information will be provided as it becomes available.
22/7/2024 - The construction contract has been awarded. Works are planned to start in September 2024 with a target completion date anticipated for early 2025.
27/6/2024 - The last update for this project is still current. Further updates will be provided as new information becomes available. Subscribe to this page for updates.
09/05/2024 - The tender for the repair works has now closed with tender submissions currently under review.
12/04/2023 - The tender for the repair works has been released.
15/02/2024 - Council has received funding approval to undertake repairs to the Island Point Jetty. Tender documents are currently being prepared.