Bamarang Road - Bamarang - Major Landslips (2)
Announcement
Two (2) major landslip sites and related repair works are completed on Bamarang Road.
The Shoalhaven was declared a Natural Disaster Area 5 March 2022 after an East Coast Low and rain events. This had a major impact on Kangaroo Valley and surrounding communities, landslips affecting roads and property. Bamarang Road, Bamarang, was severely impacted by these events.
- Public access
open
No restrictions
- Where
Bamarang Road, Bamarang 2540
- Project StatusCompleted
- Last reviewed
11 September 2024
The latest
Two (2) major landslips and related repair works are completed on Bamarang Road.
Select image to view completed landslip at Site 1
About the works
Major landslips repaired (2)
Site 1 SH00290 near rural address 325 and Site 2 DM00899 near rural address 319 - major landslips are completed. See Site 2 completed landslip below.
This project was part of the Major Landslip Package 2022, delivery of 38 fully remediated landslips across 15 roads, with final completion November 2024. Council thanks residents for their patience and understanding through the delivery of this critical project.
This project was jointly funded by the Australian Government and NSW Government under the Disaster Recovery Funding Arrangements.
2023 Works History
-
08/08/2023 - Site 1. SH00290 Works start 1 November through to 19 December 2023. Site 2. DM00899 Works start 17 January through to 31 January 2024.
Landslip damages scheduled for repair work following severe weather events
-
- 30/03/2023 - Landslip design plan for Bamarang Road is attached. Located under - Related Documents.
- 04/03/2023 - The latest construction program proposed by contractor Symal for the 38 the Major Landslip repair work has been released. The construction program lists the planned start and finish date for each of the 38 land slips. A summary of the construction program is available on the Major Landslip Package Planned Program of Work. A copy of the construction program is also available on the right-hand side of the Master Project Page in the related documents section.
- 14/2/2023 - Contract awarded - Council has resolved to proceed with the appointment of infrastructure and construction group Symal to repair the 38 major landslips. Council has provided Symal a schedule of works which prioritises the most urgent landslips with the first round of works to begin in late March 2023. To view the list of major landslips and the assigned construction priorities, refer to the Major landslip package priorities on the Master Project Page
2022 Works History
22/12/2022 - Four tenders for the repair of 38 landslips were received. A comprehensive evaluation process has been completed and a recommendation has been forwarded to Public Work Advisory (PWA)for endorsement. It is anticipated that PWA will evaluate the tender acceptance report and respond to Council mid-January. Further information can be found on theMaster Project Page
03/11/2022 - Following months of geotechnical investigations, design work and tender preparation, Council is now seeking contractors to bid on the 38 landslips deemed a priority. Submissions close 6 December 2022.Shoalhaven Area – Remediation of Multiple Slips – RFT – 10053781.
10/10/2022 - Following record rain events, Council has recorded 98 landslides as a high priority, with a focus on 38 sites that are deemed most urgent. We've now finished geotechnical investigations at these 38 sites, leading the way for designs to be completed in the coming weeks. The designs form part of a works package that will go out to tender in October.