30/9/2024 - Site clean-up works are scheduled from Tuesday 8 October to Thursday 10 October 2024 to complete this pavement repair works program, weather permitting.
1/9/2024 - The contractor is currently undertaking pavement defect rectification works which are expected to be completed by Friday 6 September 2024.
16/8/2024 - Pavement repair works are complete; however, Councils contractor will return to site late-August to rectify some pavement defects.
25/07/2024 - Pavement repair works are complete. In mid-August the contractor will return to site to rectify some pavement defects. Updates will be posted here.
11/07/2024 - Pavement repair works are complete. The contractor will return to site in early August to rectify some pavement defects.
05/07/2024 - Pavement repair works are complete. Line marking to be completed mid-July 2024.
18/06/2024 - Council’s contractor is carrying out works on the remaining patches on Bendalong Rd and Inyadda Dr. Works are scheduled to be completed by the end of June 2024, weather permitting.
03/06/2024 - The council contractor is carrying out works on the remaining patches on Bendalong Road before starting repair works on Inyadda Drive.
23/5/2024 - Stage one of repair works, patches on Bendalong Road, were bitumen sealed Wednesday 22 May 2024. Please reduce speed and follow aftercare speed restrictions as repaired sections are yet to be line marked. Council’s contractor returns mid next week to stabilise works on remaining Bendalong Rd patches before starting repairs on Inyadda Dr.
15/5/2024 - Announcement: Reduce speed & drive to conditions. Day and night traffic control is in place to Monday 13 May 2024. Pilot vehicles will escort vehicles though the site, one direction at a time. The contractor is monitoring the site over the weekend. Please reduce speed and drive to conditions. Road works are on hold and will start again when the weather permits. Subscribe to this page for updates.
10/5/2024 - Drive to conditions. Bendalong Rd has been impacted by ongoing wet weather this week. With unsealed sections of road and potential for conditions to deteriorate, please reduce speed and drive to conditions. Roadworks have been impacted by ongoing rain and are on hold. Roadworks will start again when weather permits.
7/5/202 - Announcement: Drive to conditions. Bendalong Rd has been impacted by ongoing wet weather this week. With unsealed sections of road and potential for conditions to deteriorate, please reduce speed and drive to conditions.
Repair works on hold. Due to the ongoing heavy rainfall repair works on Bendalong Rd are on hold. Repair works will start again when the weather permits. Subscribe to this page for updates
19/4/2024 - Announcement: Pavement repair works have started. Works will be carried out under traffic control; minor delays may be experienced. Works are expected to take four (4) weeks to complete, weather permitting.
2/4/2024 - Announcement: Repair works to start. Contractor Roadworx has scheduled necessary pavement repair works to start Monday 15 April 2024. Works will be carried out under traffic control; minor delays may be experienced. Repair works are expected to take 4 weeks to complete, weather permitting.
05/03/2024 - Pavement repair works are scheduled by the contractor to commence mid-April 2024. Works are expected to take 4 weeks to complete, weather permitting.
29/02/2024 - Tender awarded in December 2023 to Roadworx Pty Ltd.
16/02/2024 - Road works on Bendalong Road are expected to commence in April 2024.