22/12/2022 - Four tenders for the repair of 38 landslips were received. A comprehensive evaluation process has been completed and a recommendation has been forwarded to Public Work Advisory (PWA)for endorsement. It is anticipated that PWA will evaluate the tender acceptance report and respond to Council mid-January. Further information can be found on the Master Project Page
03/11/2022 - Following months of geotechnical investigations, design work and tender preparation, Council is now seeking contractors to bid on the 38 landslips deemed a priority. Submissions close 6 December 2022.Shoalhaven Area – Remediation of Multiple Slips – RFT – 10053781.
18/09/2022 - Following record rain events, Council has recorded 98 landslides as a high priority, with a focus on 38 sites that are deemed most urgent. We've now finished geotechnical investigations at these 38 sites, leading the way for designs to be completed in the coming weeks. The designs form part of a works package that will go out to tender in October.
16/09/2022 - Geotechnical engineers will be conducting a site investigation on Browns Mountain Road, from Wednesday 7th September 2022. Borehole drilling will be conducted to inform the design.
02/09/2022 - Across the Shoalhaven, of the 98 landslides that were of highest priority, a consolidated scope of 35 will form a tender package that will be going out to market prior to Christmas. Included within that tender package is, amongst others, Woodhill Mountain, Wattamolla, and Bunkers Hill Road. The start date of contract work is likely in the new year, in the interim, regular surveillance continues.
27/07/2022 - Geotechnical investigations for Browns Mountain Road are currently re investigated due to the change in landslip structure that developed from the July weather event. The investigation will include the scope to identify additional landslides.
07/07/2022 - Browns Mountain Road currently has restricted access with one lane due to worsening weather conditions.
30/06/2022 - Geotechnical onsite investigation continued this week with stage 1 draft ready for submission.
23/06/2022 - Further Geotechnical investigations are currently being undertaken.
16/06/2022 - Design has been drafted for rectification with contractor engagement underway.
09/06/2022 - Traffic continues to be limited to residents only.
02/06/2022 - Restrictions remain in place with traffic being limited to residents only.
26/05/2022 - Works currently on track with Geotechnical investigation analysis design in progress.