14/08/2023 - A full road closure for 1 hour only, from 12.30pm to 1.30pm on Monday 21 August 2023 near property 246 Bundewallah Road, is required to complete pavement works.
For more details see Related documents - Bundewallah Road residents letter 14 August 2023.
28/07/2023 - Works to repair the damaged sections of road are currently being undertaken and are expected to be completed mid August 2023.
21/07/2023 - The last update for this project is still current. Further updates will be provided as new information becomes available.
16/05/2023 - Works to repair the damaged sections of road have been approved by Transport NSW with Council contribution, and will be undertaken by Council's Roads Unit in the coming weeks.
06/04/2023 - A quotation for ground investigations and pavement designs has been issued. Once complete, pavement designs will be submitted to Transport NSW for scope of work and funding approval.
23/03/2023 - A quotation for ground investigations and pavement designs will be issued in April 2023 prior to submitting to Transport NSW for scope of work and funding approval.
02/03/2023 - A Geotechnical Engineer is being engaged to carry out pavement investigation works.
Council are engaging Geotechnical engineers to undertake pavement investigations to provide advice on repair works, prior to Tendering.