Croobyar Road - Croobyar - Smarts Bridge Replacement

Replacement of deteriorated bridge. Work involves the construction of a new, more durable concrete and steel bridge to replace the existing timber bridge.

  • Public access
    open
  • No restrictions
  • Where Croobyar Road, Croobyar 2539
  • Estimated completion date15 October 2024
  • Project StatusIn Progress
  • Last reviewed 20 November 2024

The latest

20/11/2024 - Project is complete.

About the works

Council has successfully been awarded grant funding by TfNSW under the Fixing Country Bridges program to replace this bridge with a new, more durable concrete and steel bridge.

The current project schedule is as follows:

  • Project Tendering - April 2024
  • Contract Awarded - June 2024
  • Design Phase of the Contract - June to July 2024
  • Construction - August to November 2024

Please subscribe to stay updated on this project. 

History

  • 24/10/2024 - There has been a delay in the seal of the road approaches. The new seal date is Friday 08 November, weather permitting.
  • 23/09/2024 - Bridge is complete and operational. Road approaches are complete pending seal which will occur on Wednesday 09 October, weather permitting.
  • 27/08/2024 - Construction in Progress. Bypass track operational.
  • August 2024 Update - Construction to commence on Thursday 08 August 2024. Refer to resident notification letter for further details.
  • July 2024 Update - Design finalisation and preworks documentation is in progress. Potential start of construction in August 2024.
  • June 2024 Update - The contract has been awarded and the design phase has commenced.
  • May 2024 Update - Tender evaluation in progress.
  • April 2024 Update - Design and Construct tender submissions due 10 May 2024.
  • January 2024 Update - Project to be tendered as a design & construct contract in February 2024.

 