Completed pavement repair work along Fishermans Paradise Road
30/9/2024 - Site clean-up works are scheduled from Tuesday 8 October to Thursday 10 October 2024, to complete this pavement repair works program, weather permitting.
1/9/2024 - Pavement repairs are completed; clean-up works to be carried out.
16/8/2024 - Pavement repair works are complete, and line marking will be completed late August, weather permitting.
25/7/2024 - Pavement repair works are complete. Line marking will be completed early August, weather permitting.
5/7/2024 - Works are rescheduled by the contractor to start mid-July 2024 and are expected to take 2 weeks to complete, weather permitting.
18/06/2024 - Pavement repair works are scheduled by the contractor to start in early July 2024. Works are expected to take 2 weeks to complete, weather permitting.
6/03/2024 - Pavement repair works are scheduled by the contractor to start mid-June 2024. Works are expected to take 2 weeks to complete, weather permitting.
07/05/2024 - Pavement repair works are scheduled by the contractor to start in late May 2024. Works are expected to take 2 weeks to complete, weather permitting.
05/03/2024 - Pavement repair works are scheduled by the contractor to commence late May 2024. Works are expected to take 2 weeks to complete, weather permitting.
29/02/2024 - Tender awarded in December 2023 to Roadworx Pty Ltd.
Below: Road deterioration from back-to-back severe weather events