The Shoalhaven was declared a Natural Disaster Area after the March 2022 East Coast Low and subsequent rain events caused extensive damage to many Council assets. Fishermans Paradise Road was severely impacted and extensive road repair works are required.

The latest

5/11/2024 - Pavement repair works are completed. This project was funded by the NSW Government under the Disaster Recovery Funding Arrangements.

Select image to view completed pavement repairs

About the works

Completed pavement repair work along Fishermans Paradise Road  

Fishermans Paradise Rd - completion - Adam 31Jul24.JPG

2024 Works history

Completed pavement repair work along Fishermans Paradise Road 

Fishermans Paradise Rd - completion 1 - Adam 31Jul24.JPG  Fishermans Paradise Rd - completion 2 - Adam 31Jul24.JPG

30/9/2024 - Site clean-up works are scheduled from Tuesday 8 October to Thursday 10 October 2024, to complete this pavement repair works program, weather permitting.

1/9/2024 - Pavement repairs are completed; clean-up works to be carried out. 

16/8/2024 - Pavement repair works are complete, and line marking will be completed late August, weather permitting. 

25/7/2024 - Pavement repair works are complete. Line marking will be completed early August, weather permitting.

5/7/2024 - Works are rescheduled by the contractor to start mid-July 2024 and are expected to take 2 weeks to complete, weather permitting.

18/06/2024 - Pavement repair works are scheduled by the contractor to start in early July 2024. Works are expected to take 2 weeks to complete, weather permitting. 

6/03/2024 - Pavement repair works are scheduled by the contractor to start mid-June 2024. Works are expected to take 2 weeks to complete, weather permitting.

07/05/2024 - Pavement repair works are scheduled by the contractor to start in late May 2024. Works are expected to take 2 weeks to complete, weather permitting.

05/03/2024 - Pavement repair works are scheduled by the contractor to commence late May 2024. Works are expected to take 2 weeks to complete, weather permitting.

29/02/2024 - Tender awarded in December 2023 to Roadworx Pty Ltd.

Below: Road deterioration from back-to-back severe weather events

fishermans paradise.JPG

 

2023 Works history

15/11/2023 - Tender is expected to be awarded in December 2023 with works commencing in early 2024.

14/09/2023 - Project scope and estimate have been updated to reflect TfNSW updated requirements. Works are being incorporated into a large contract addressing pavement remediation for five main roads in the Southern District. Tenders are expected to be advertised by the end of September with works to commence early in the new year, dependent on Council’s consideration and contractor availability.

27/07/2023 - Project scope and estimate have been updated to reflect TfNSW requirements. Works are being incorporated into a large contract addressing pavement remediation for five main roads in the Southern District. Tenders are expected to be advertised by the end of July with works to commence later this year, dependent on Council’s consideration and contractor availability.

24/05/2023 - Ground investigations and pavement designs have been completed and submitted to TfNSW. Repair works are pending TfNSW approval.

12/04/2023 - Council have undertaken interim works whilst awaiting TfNSW approval.

11/04/2023 - Ground investigations and pavement designs have been completed and submitted to TfNSW. Repair works are pending TfNSW approval. Council anticipates TfNSW to respond by June 2023 at which time tenders for construction can be called in August 2023. Included in this tender will be works associated with damages recorded on other roads in Fishermans Paradise including: Alma Avenue, Anglers Road, Wattle Street, Cornfield Parade.  *See map view of damage locations provided in related documents.

24/03/2023 - Ground investigations are underway. Pavement designs will be submitted to TfNSW for approval in April 2023. Interim works by the District to address the pavement conditions will be carried out in April

02/02/2023 - Field work for sampling and testing of the pavement is currently being carried out.19/01/2023 - Sampling and testing will be carried out late January / early February 2023 to inform the repair method.

19/01/2023 - A geotechnical consultant has been engaged to commence sampling and testing works to inform the repair method. Field work will be carried out late Jan/early Feb. Following geotechnical investigations and approval of the scope of work by transport, works will be Tendered for construction. In the interim please drive slowly with caution.

 

2022 Works history

21/22/2022 - Tender expected in February 2023 following sampling and testing investigations.

21/11/2022 - A Southern District Pavement Repair Program, including sections of Fishermans Paradise Road, is expected to be put to tender in February 2023 following geotechnical investigations. In the interim please drive slowly with caution.

01/11/2022 - A tender to deliver a Southern District Pavement Repair Program, including sections of Fishermans Paradise Road is expected to be called in December 2022. Road rehabilitation works are expected to commence along sections of Fishermans Paradise Road and Alma Road in the new year.

 

 