23/08/23 - Natural Disaster funded repair works have been completed. Council will continue to monitor the condition of the road and undertake repairs where required.
20/07/2023 - Asphalt works are complete with final line marking still to be undertaken. Temporary markers have been installed for the interim.
04/07/2023 - Night works have commenced at Site 1 and 2, Sunday 2nd July and anticipated to be completed within 2 weeks, weather permitting.
22/06/2023 - Night works are delayed one (1) week and are due to commence at site 1 and 2, Sunday 2nd July and anticipated to be completed within two (2) weeks, weather permitting.
20/06/2023 - Night works are due to commence at Site 1 and Site 2, Sunday 25 Jun. Works are anticipated to be completed within two (2) weeks, weather permitting.
31/05/2023 - Funding has been approved by Transport for NSW for sections of Greenwell Point Rd. See 'Asphalt patch repair work schedule' in Related Documents.
25/05/2023 - Site 1. 300m between Apperleys Lane and Mottrams Lane and Site 2. 400m in proximity to Stratherick Lane pavement repair works: TfNSW has approved funding to repair damaged pavement adjacent previous asphalt repairs. A request for quote has been issued with works planned for June.
25/05/2023 - Site 3. From Rayleigh Drive to Apperleys Lane: TfNSW has approved ground investigations to determine the appropriate repair method. An RFQ has been issued with the investigation anticipated to be completed in July.
17/05/2023 - Maintenance staff are undertaking weekly inspection of the road and actioning temporary road repairs as required.
27/04/2023 - Council has received Natural Disaster Recovery Funding to repair damaged sections of Greenwell Point Road. A request for quote is being prepared and will be issued in April with works anticipated to commence in June, subject to contractor availability and weather conditions.
13/04/2023 - Maintenance staff are undertaking weekly inspection of the road and actioning temporary road repairs as required.
06/04/2023 - Maintenance staff will undertake weekly inspection of the road and schedule temporary pothole repairs as required.
29/03/2023 - Temporary pavement repairs are being completed at this location prior to Easter (pothole repairs and large shoves).
17/03/2023 - Council has received Natural Disaster Recovery Funding to repair damaged sections of Greenwell Point Road. A request for quote is being prepared with works anticipated to commence in April, subject to contractor availability and weather conditions.
02/03/2023 - Sampling and testing investigations have been completed. Reports are to be reviewed and submitted for funding approval to Transport for NSW.