Landslip repair works nearing completion on Hughes Road November 2023
Landslip repair works under construction
08/08/2023 - Landslip Site 1. DM00610 Works commence 13 November through to 24 November 2023. Site 2. DM00611 Works commence 21 November through to 12 December 2023.
26/06/2023 - The latest update for this project is current. Further updates will be provided as new information becomes available.
30/03/2023 - Landslip design plan for Hughes Road is attached. Located under - Related Documents.
17/03/2023 - Kangaroo Valley Information Session on Friday 17 March, 7pm - 8pm (followed by BBQ) at KV Community Hall. Meet contractor Symal and get briefing on the start of landslip works.
04/03/2023 - The latest construction program proposed by contractor Symal for the 38 the Major Landslip repair work has been released. The construction program lists the planned start and finish date for each of the 38 land slips. A summary of the construction program is available on the Major Landslip Package Planned Program of Work. A copy of the construction program is also available on the right-hand side of the Master Project Page in the related documents section.
15/2/2023 - Contract awarded - Council has resolved to proceed with the appointment of infrastructure and construction group Symal to repair the 38 major landslips. Council has provided Symal a schedule of works which prioritises the most urgent landslips with the first round of works to begin in late March 2023. To view the list of major landslips and the assigned construction priorities, refer to the Major landslip package priorities on the Master Project Page