01/11/2023 - Council has received Natural Disaster and Infrastructure Betterment funding to carry out pavement repair work on Illaroo Road. The repairs will take place from West Cambewarra Road to Browns Mountain Road. The design process is currently underway, and repairs are expected to be carried out in the new year, following design and tendering for construction.
25/05/23 - Ground investigations and pavement designs have been completed and submitted to Transport NSW. Tenders are ready for advertising pending Transport NSW approval.
24/03/2023 - Reconstruction and repair work will extend over approximately 9.5km and be predominantly characterised by two different treatment types.
23/03/2023 - Ground investigations and pavement designs have been completed and submitted to Transport NSW. Tenders are ready for advertising pending Transport NSW approval.
02/02/2023 - Geotechnical Investigations for pavement repairs have been carried out to inform appropriate repair methods. Council are currently waiting for Transport NSW to approve the repair method before works can be Tendered for Construction.
19/01/2023 - Council has submitted a request to transport to approve the repair method before works can be tendered for construction.
19/01/2023 - Geotechnical Investigations for pavement repairs have been carried out to inform appropriate repair methods. Council is currently pending transport to approve the repair method before works can be tendered for construction. A temporary 60km/h speed zone and pothole warning signs have been installed to inform motorists the condition of the road.