6/11/2024 - Line marking will be carried out next week, Wednesday 13 November and Thursday 14 November 2024, weather permitting.
18/10/2024 - Repair works have started on Jervis Bay Road and are proceeding as per the works program towards expected completion by late October 2024, weather permitting. Find more details under - About the works.
Announcement - Repair works have started on Jervis Bay Road and are proceeding as per the works program towards an expected completion by late October 2024, weather permitting. Traffic control is in place with one lane stop/go traffic flow. Motorists are advised to allow extra travel time during works.
25/9/2024 - Councils' contractor, Fulton Hogan, plan to establish to site Friday 11 October 2024 and start repair works at Site 4 near rural address 608 from Monday 14 October 2024, weather permitting.
23/9/2024 - Council has identified the preferred contractor for pavement rectification works. The program for the rectification works is expected to be confirmed soon. Find more details on the four (4) main repair sites under - About the works.
12/9/2024 - Request for quotations have been received. Further information and updates will be provided as the tender evaluation concludes. Subscribe to this page for updates.
13/8/2024 - Request for quotations have been made to road contractors to carry out road remediation (repair) work. Updates will be provided here as new information becomes available.
25/7/2024 - Tender documents are prepared and due to be released in the coming weeks. Updates will be provided here as new information becomes available.