Lake Conjola Entrance Road - Yatte Yattah - Pavement Repair

The Shoalhaven was declared a Natural Disaster Area after the March 2022 East Coast Low and subsequent rain events caused extensive damage to many Council assets. Lake Conjola Entrance Road was severely impacted and extensive road repair works are required.

The latest

5/11/2024 - Pavement repair works are completed. This project was funded by the NSW Government under Disaster Recovery Funding Arrangements.

Select image to view completed pavement repairs

About the works

Pavement repair works are completed

Lake Conjola Ent Rd - completion pavement 3a - Recover Aug24.jpg

2024 Works history

30/9/2024 - Site clean-up works are scheduled for this Thursday 3 October and Friday 4 October 2024 to complete this repair works program.

16/8/2024 - Pavement repair works are complete; site clean-up works to be done in the coming weeks.

25/7/2024 - Pavement repair works are complete. The contractor will be returning to site mid-August to rectify some pavement defects. 

5/7/2024 - Pavement repair works are rescheduled by the contractor to start in late-July 2024. Works are expected to take 2.5 weeks to complete, weather permitting. Start date is rescheduled due to recent and ongoing rain events.

18/06/2024 - Pavement repair works are scheduled by the contractor to commence mid-July 2024. Works are expected to take 2.5 weeks to complete, weather permitting. Start date rescheduled due to recent and ongoing rain events.

03/06/2024 - Pavement repair works are now scheduled by the contractor to start late June 2024. Works are expected to take 2.5 weeks to complete, weather permitting. Start date rescheduled due to recent and ongoing rain events.

07/05/2024 - Pavement repair works are scheduled by the contractor to start early in June 2024. Works are expected to take 2.5 weeks to complete, weather permitting. Start date rescheduled due to recent rain events.

05/03/2024 - Pavement repair works are scheduled by the contractor to commence early May 2024. Works are expected to take 2.5 weeks to complete, weather permitting.

29/02/2024 - Tender awarded in December 2023 to Roadworx Pty Ltd.

 

2023 Works history

15/11/2023 - Tender is expected to be awarded in December 2023 with works commencing in early 2024.

27/07/2023 - Project scope and estimate have been updated to reflect TfNSW requirements. Works are being incorporated into a large contract addressing pavement remediation for five main roads in the Southern District. Tenders are expected to be advertised by the end of July with works to commence later this year, dependent on Council’s consideration and contractor availability.

24/05/23 - Ground investigations and pavement designs have been completed and submitted to TfNSW. Repair works are pending TfNSW approval.

06/04/2023 - Ground investigations and pavement designs have been completed and submitted to TfNSW. Repair works are pending TfNSW approval.

24/03/2023 - Ground investigations are underway. Pavement designs will be submitted to TfNSW for approval in April 2023.

02/02/2023 - Field work for sampling and testing of the pavement is currently being carried out.

2022 Works history

Rapid road deterioration from severe weather events

Lake conjola entrance rd.JPG

21/12/2022 - Tender expected in February 2023 following sampling and testing investigations.

21/11/2022 - A Southern District Pavement Repair Program, including sections of Lake Conjola Entrance Road, is expected to be put to tender in February 2023 following geotechnical investigations. In the interim please drive slowly with caution.

01/11/2022 - An open tender to deliver a Southern District Pavement Repair Program is expected to be called in December 2022. Road rehabilitation works will be completed along several sections of Lake Conjola Entrance Road commencing next year. 

 

 

 