22/12/2022 - Four tenders for the repair of 38 landslips were received. A comprehensive evaluation process has been completed and a recommendation has been forwarded to Public Work Advisory (PWA)for endorsement. It is anticipated that PWA will evaluate the tender acceptance report and respond to Council mid-January. Further information can be found on the Master Project Page
03/11/2022 - Following months of geotechnical investigations, design work and tender preparation, Council is now seeking contractors to bid on the 38 landslips deemed a priority. Submissions close 6 December 2022.Shoalhaven Area – Remediation of Multiple Slips – RFT – 10053781.
30/09/2022 - Following record rain events, Council has recorded 98 landslides as a high priority, with a focus on 38 sites that are deemed most urgent. We've now finished geotechnical investigations at these 38 sites, leading the way for designs to be completed in the coming weeks. The designs form part of a works package that will go out to tender in October.
07/09/2022 - Geotechnical engineers will be conducting a site investigation on Mount Scanzi Road, Thursday 8th September 2022. The road will be open, under traffic control.
02/09/2022 - Across the Shoalhaven, of the 98 landslides that were of highest priority, a consolidated scope of 35 will form a tender package that will be going out to market prior to Christmas. Included within that tender package is, amongst others, Woodhill Mountain, Wattamolla, and Bunkers Hill Road. The start date of contract work is likely in the new year, in the interim, regular surveillance continues.
27/07/2022 - Geotechnical investigations for Mount Scanzi Road are currently being re investigated due to the increase of landslips that developed from the weather event this month. It has been identified there are an additional 11 new landslips on this road being investigated. This road is currently under restricted access with one lane.
07/07/2022 - Mount Scanzi Road currently has restricted access with one lane due to worsening weather conditions.
30/06/2022 - Geotechnical onsite investigation continued this week with stage 1 draft ready for submission week commencing 4th July 2022.
23/06/2022 - Investigations are ongoing.
6/06/2022 - Works currently on track with Geotechnical investigation analysis design in progress.
09/05/2022 – Road has now been cleared and fallen trees have been removed. Road conditions have returned to normal. Geotechnical investigation for landslip scheduled to commence next week.
02/06/2022 – Preliminary design studies have begun. Works have commenced for tree and debris clearing. Due to these works commuters are advised that delays may be encountered.
26/05/2022 - Investigation design work on track for week commencing 30th May 2022.