Major landslip and road repair works are completed.
14/08/2023 - Due to recent wet weather and adverse ground conditions closures for Suffolk Rd are now expected until Friday18 August 2023.
08/08/2023 - Repair works started from Thursday 3 August through to Tuesday 15 August 2023.
29/07/2023 - Contractor Symal has revised works commencement start date to Thursday 3 Aug 2023.
26/07/2023 - Contractor Symal advises that work on Suffolk Rd in the vicinity of rural address 48 is planned to commence on Tuesday 1 Aug 2023. All work along Suffolk Road will be undertaken Mondays to Fridays between 7:30am and 4:30pm and will involve a full road closure to vehicles and pedestrians. For more details see 'Temporary Closure - Letter to Residents - 26 July 2023' under Related Documents.
30/03/2023 - Landslip design plan for Suffolk Road is attached. Located under Related Information.
04/03/2023 - The latest construction program proposed by contractor Symal for the 38 the Major Landslip repair work has been released. The construction program lists the planned start and finish date for each of the 38 land slips. A summary of the construction program is available on the Major Landslip Package Planned Program of Work. A copy of the construction program is also available on the right-hand side of the Master Project Page in the Related Documents section.
15/02/2023 - Contract awarded - Council has resolved to proceed with the appointment of infrastructure and construction group Symal to repair the 38 major landslips. Council has provided Symal a schedule of works which prioritises the most urgent landslips with the first round of works to begin in late March 2023. To view the list of major landslips and the assigned construction priorities, refer to the Major landslip package priorities on the Master Project Page.