Repair works in progress
Below: Site 1 near rural address 552 landslip repair works underway and nightworks 16 November.
Below: Site inspection of repair works 8 November with Symal and Council senior project managers.
Below: Night works under construction 9 November.
Below: Initial clearing and preparation for landslip repair works.
1/7/2023 to 22/12/2023 – The updated three-week Lookahead program was released each week by contractor, Symal, and published on this page by council weekly, under ‘Related Information’. Repair works progress and road closures were also detailed weekly for all sites under ‘About the works’.
30/6/2023 - Updated two-week look-ahead program released by Symal. Refer Related Information.
27/6/2023 - Updated two-week look-ahead program released by Symal. Refer Related Information.
21/06/2023 - Contractor Symal releases revised construction program. See 'Construction Program - Remediation - Multiple slips - Shoalhaven' under Related Information.
15/06/2023 - Local sub-contractor A&D Tree Services commences tree trimming works in preparation for Symal contractor works.
05/06/2023 - Updated two-week look-ahead program released by Symal. Refer Related Information.
16/05/2023 - Updated two-week look-ahead program released by Symal. Refer Related Information.
08/05/2023 - Mobilisation of construction equipment to commence soon. Updated two-week Lookahead program released by Symal. Refer Related Information
30/03/2023 - Landslip design plan for Woodhill Mountain Road is attached. Located under - Related Information
30/03/2023 - Landslip repair drop-in sessions: THURS 30 March 4 – 5pm THURS 13 April 4 – 5pm. Drop by the Kangaroo Valley Hall (177 Moss Vale Rd) where Symal and Council will answer your questions about upcoming roadworks.
17/03/2023 - Kangaroo Valley Information Session on Friday 17 March, 7pm - 8pm (followed by BBQ) at KV Community Hall. Meet contractor Symal and get briefing on the start of landslip works.
04/03/2023 - The latest construction program proposed by contractor Symal for the 38 the Major Landslip repair work has been released. The construction program lists the planned start and finish date for each of the 38 land slips. A summary of the construction program is available on the Major Landslip Package Planned Program of Work. A copy of the construction program is also available on the right-hand side of the Master Project Page in the related documents section.
15/2/2023 - Contract awarded - Council has resolved to proceed with the appointment of infrastructure and construction group Symal to repair the 38 major landslips. Council has provided Symal a schedule of works which prioritises the most urgent landslips with the first round of works to begin in late March 2023. To view the list of major landslips and the assigned construction priorities, refer to the Major landslip package priorities on the Master Project Page