3/10/2024 - Pavement asphalt wearing surface is scheduled for installation November 2024. Updates will be provided here. Subscribe to this page for updates.
13/8/2024 - Updated road signage is scheduled for week starting 12 August 2024. When confirmed, further updates on the scheduled wearing course and permanent line marking to follow will be advised here. Subscribe to this page for updates.
15/7/24 - Temporary line marking, guideposts and guardrail have been completed on Yalwal Road. Updated Road Signage requirements are confirmed and on order (to be installed as soon as possible). The final wearing course is scheduled for Spring 2024. Permanent line marking will be installed shortly after.
04/06/2024 – The base layer of asphalt is completed. Temporary line marking, guideposts and guardrail are planned to be installed early July. The final wearing course (Stone Mastic Asphalt) is postponed until the ambient temperature increases substantially (between October-December 2024).
15/5/2024 - Despite the recent heavy rainfall through May, works have progressed relatively well with the heavily bound base layer approximately 50% completed. When it's completed, the asphalt wearing course will start, project completion is expected late June 2024, weather permitting.
02/04/2024 - Contractor, Cleary Bros, have advised works are planned to start Wednesday 3 April 2024, weather permitting. Works are due for completion by end of June 2024.
20/03/2024 - Contracts have been awarded. Cleary Bros will be establishing to site in the coming week with scheduled start date Wednesday 3 April. Works are expected to be completed by end of June 2024.