Yalwal Road - Yarramunmun Creek Bridge - Flood Repairs

Find information on 7 April 2024 natural disaster storm event (AGRN1119) that severely damaged Yalwal Rd and the eastern approach to Yarramunmun Bridge, and the repair works.

Also, 28 November 2023 natural disaster flood event AGRN1086 that severely damaged Yalwal Road, and repairs completed February 2024.
Also, construction details of the new concrete Yarramunmun Creek Bridge completed May 2023.

The latest

Yalwal Rd is now open.

Select image for a closer look at recent road repairs.

About the works

Below: Damages following 7 April 2024 (AGRN 1119) severe weather and flooding event. 

20240407_214627541_iOS.jpg

2024 Flood event repair works history

9/5/2024 - Temporary Closure: Due to extended periods of wet weather the final reconstruction works have been delayed. The road closure is anticipated to extend to Friday 17 May 2024.

3/5/2024 - Temporary ClosureRecovery works to provide temporary access to Yalwal Road are extended to Friday 10 May 2024. Personnel will be onsite to assist residents during this time. Access through the site is limited to residents only. Severe flood damage to Yalwal Road has occurred again, following the declared natural disaster 7 April 2024 (AGRN1119) severe weather event. Subscribe to this page for updates.

10/4/2024 - As a result of the recent severe weather event 7 April 2024 and significant damage to the eastern approach to Yarramunmun Bridge, Yalwal Road is closed.

 

2024 Yarramunmun Bridge repairs

Natural Disaster Flood Event (AGRN1086) 28 November 2023 caused significant damage to the road approaches on Yalwal Road, with heavy deposits of tree debris. Temporary road repairs to restore access are planned to be completed by 22 December 2023. Final road repairs are planned for February 2024.

Below: February 2024 Yarramunmum Bridge repaired following natural disaster (AGRN 1086).

Yalwal Rd - repairs from Nov23 ND - Aaron - 28Feb24.jpg

Below:  Natural Disaster Flood Event (AGRN1086) 28 November 2023 and the immediate repair works.

Yarramunmun Storm Event - DL - 30Nov23 .jpeg Yarramunmun flood event cleanup - DL - 30Nov23.jpg

2024 Bridge repair works history

11/4/2024 - Temporary ClosureRecovery works to provide temporary access to Yalwal Road are planned for 2 weeks starting Thursday 11 April through to Friday 26 April 2024. Personnel will be onsite to assist residents during this time. Severe flood damage to Yalwal Road has occurred again following the recently declared natural disaster 7 April 2024 (AGRN1119) Flood and Storm event. Subscribe to this page for updates.

27/02/2024 - Yalwal Road will be open from Wednesday 28 February 2024. 

22/01/2024 -Announcement: Temporary Road closure ongoing. Yalwal Road at Yarramunmun Creek bridge is closed due to recent flood damage. Resident and construction traffic access only - no public access. Temporary road repairs to restore access are planned to be completed by 16 February 2024.

16/01/2024 – Repair works to the bridge have commenced and are anticipated to be completed by 16 February 2024.

2023 Bridge repair works history

18/12/2023 - Road closure: no public access at Yarramunmun Creek bridge due to recent flood damage. Resident and construction traffic access only.

28/11/2023 - Natural Disaster Flood Event AGRN1086 caused significant damage to road approaches with heavy deposits of tree debris. Temporary road repairs to restore access planned to be completed by 22 December 2023. Final road repairs planned for February 2024.

 

2023 Yarramunmun Creek Bridge replacement

Design and construction of a twin-span, single lane concrete bridge to replace the existing timber bridge over Yarramunmun Creek has been funded jointly by Council and TfNSW under the NSW Fixing Country Bridges program, it is planned for completion by mid-May 2023.

Below: New concrete bridge over Yarramunmun Creek and necessary road works nears completion.

Yarramunmun Creek 2.jpg

2023 Works history

05/06/2023 - Bitumen sealing of road approaches completed.

28/05/2023 - A major accomplishment has been the bitumen sealing of the road approaches, which will assist shield the new roadwork from the elements. There is still plenty to accomplish, including the building of earthworks and retaining walls next to the north-eastern approach, the installation of steel crash barriers, the placement of signs, and earth stabilisation work, even though the project is anticipated to be finished in the next three weeks. Impact on traffic will be minimal.

20/05/2023 - Road pavement construction along both approaches to the bridge is nearing completion and will soon be ready for bitumen sealing. Steel crash barrier installation will then be completed before the old timber bridge is removed. Yalwal Rd will need to be closed for several hours within the next week to allow the bitumen sealing to take place. A further public announcement confirming road closure date and times will be made as soon as the date for bitumen sealing is confirmed.

31/03/23 - “All hands on deck”. Up to 8 “men at work” were required today to place over 50 cubic meters of premixed concrete for the twin span bridge deck.

31/03/23 “All hands on deck”. Up to 8 “men at work” were required today to place over 50 cubic meters of premixed concrete for the twin span bridge deck.

Yalwal 2.jpg

 

27/03/23 -  Following installation of the bridge abutments, central headstock and rock scour protection, the four (4) prefabricated steel formwork / steel reinforced deck units were carefully lowered into place onto the abutments and headstock. Next week, steel reinforcement tie bars will be fixed in place and the deck formwork units will be filled with 50 cubic metres of premixed concrete.

21/03/2023 -  Yalwal Rd will be closed for 3 days between the hours of 7:30am and 4:30pm on the following days:

• Friday 24th March 2023 – at the Yarramunmun bridge site to allow placement of prefabricated steel formwork bridge decks

• Monday 27th March 2023 – between Yarramunmun Ck bridge and Yalwal Gap (2.5kms) for overhead pruning of bushfire affected trees

• Tuesday 28th March 2023 – between Yarramunmun Ck bridge and Yalwal Gap (2.5kms) for overhead pruning of bushfire affected trees.

Traffic will not be permitted past these planned road closure locations.

 

Yalwal 26.3.2023.png

Yalwal 21.03.2023.png

20/02/2023 - Nine (9) 600-mm diameter concrete piers have been drilled into the earth. To support the bridge "abutments" and centre "headstock" when the creek floods, each pier was dug at least 1000 mm into exceptionally hard rock beneath the stream bed. Steel outer casings were put in place to stop the ground from slumping into the bore holes.

Below: Bitumen sealing of road approaches being completed July 2023.

Yarramunmun Creek 3.jpg    Yarrumunmun Creek 1.jpg

 Yalwal Rd.jpg Yarramunmun Bridge,.png

Yalwal Rd 1.jpg Yalwal Rd 3.jpg

 

 

2022 Works History

12/02/2022 - Steel sheet piling is being installed around each abutment location to create a "coffer dam." Water will then be pumped out of the coffer dam when the bored piers are installed to support the bridge abutments.

28/11/2022 - The contractor is in the process of establishing themselves on site, including the erection of a secure storage compound. The existing timber bridge will remain in use for the public until the new bridge is completed.

12/11/2022 - The construction contract was awarded to local construction company Jirgens Civil P/L. Site establishment has commenced and the prefabricated steel InQuik bridge components have been delivered to site.

22/11/2022 - The contractor is in the process of establishing themselves on site, including the erection of a secure storage compound. The existing timber bridge will remain in use for the public until the new bridge is completed.

 

 

Jump to subscribe