Road Conditions

For the latest traffic information on the Princes Highway and Moss Vale Road  visit www.livetraffic.com, download the Live Traffic App or call the Transport Management Centre on 132 701.

Road Infrastructure Projects Information


Current Works
Upcoming Works
Recently Completed Works
Understanding Road Repairs


Please note that all quoted completion dates are subject to change due to weather conditions, emergencies or other unforeseen interruptions.

Latest News - Tuesday 4 December 2018

Current Works

Back Forest

Bolong Road (east of Broughton Creek) – 8.11.2018 -The works involve the widening, pavement upgrade, and resealing of approximately 1.3km of Bolong Road from 400m east of Broughton Creek. Works were temporarily halted due to excessive subsurface moisture affecting the pavement. The pavement works have now been completed, however deep lift asphalting of a short section of the road at the northern end of the recently constructed dish drain adjacent to the rockface will occur in December. Unfortunately this cannot be done sooner due to the availability of the specialist equipment required. Changed traffic conditions are operating for the duration of works. Changed traffic conditions are operating for the duration of works.  Note that where road work speed limit signs or traffic controls are displayed or used, the speed limit and controls are enforceable and must be obeyed. For further information please contact 4429 3313.

Bawley Point

Murramarang Road – Culvert installation for the community pathway project. For further information, please call 4429 8902.

Berry

Victoria Street – Rehabilitation work has commenced between Queen St to George St.  During construction detours and traffic controls will be in place.  The affected area will be closed to all but residential traffic. For more information, please contact the Roads Unit on 4406 2000.

Berry Mountain

Woodhill Mountain Road – Rehabilitation works between the new highway overpass and Broughton Vale Rd.  For more information, please contact the Roads Unit on 4406 2000.

Bomaderry

Cambewarra Road (between Warby Street and Railway Street) - an asphalt program was recently completed, weather permitting linemarking will be reinstated by the 17 December.   Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Coolangatta

Coolangatta Road, Northview Close, Edward Wollstonecraft Lane - Road resealing was recently completed, weather permitting linemarking will be reinstated by 17 December  Further information may be obtained by contacting Mr Will Lynch on 4406 2000.

Gerroa Road Upgrade & Bolong / Coolangatta Road Intersection Upgrade - 20.11.2018 – This project is completed other than linemarking of the intersection of Gerroa Road & Gerroa Road (access to Shoalhaven Heads). A reseal of the intersection of Gerroa Road & Gerroa Road (access to Shoalhaven Heads) took place on 20 November 2018 and linemarking is due to take place before 4 December 2018.  Speed reductions will be in place from 20 November to 4 December. Note that where roadwork speed limit signs or traffic controls are displayed or used, the speed limit and controls are enforceable and must be obeyed. For further information please contact the Project Manager on 4429 3313.

Culburra Beach

Prince Edward Avenue - 04.10.2018 - Scheduled for road repair. Works have now completed, only minor rectifications remaining. Final seal and line marking scheduled for mid-December.  For further information please call 4429 3224.

Falls Creek

Jervis Bay Road – Asphalt overlay at Gardener Road intersection and widening the road for a turning lane into Gardner Road.  Linemarking to be carried out mid-December.  For more information, please contact the Basin District Engineer on 4406 2000.

Kioloa

Murramarang Road – Rehabilitation work has commenced between Scerri Drive to Merry Beach Road.  During construction detours and traffic controls will be in place.  The affected area will be closed to all but residential traffic. For more information, please call 4429-8902.

Milton

Matron Porter Drive – Shared User Pathway Stage 4, the construction of approximately 700m of concrete pathway 2.5m wide between Sungrove Lane & Garside Road. For further information please call 4429 8902.

Morton/Woodburn

Wheelbarrow Road  - 1.22 kms of Wheelbarrow Road at Morton/Woodburn is scheduled to be bitumen sealed, widened with new shoulders, signage and guideposts installed. This project was put out to tender.  Tendered prices received were much higher than the 2018/19 budget allocation, so Council decided to negotiate with the two lowest tenderers in order to obtain a better price.  The road pavement design was also revised and the type of bitumen used was changed.  Both tenderers were asked to resubmit prices for the redesign.  The General Manager considered under delegation the revised pricing and a Letter of Acceptance was offered to the best tenderer on the 8th October 2018.  Since that time the contractor has been submitting the required contract documentation.  The total allocation for the work is $585,000 of which $485,000 is Commonwealth Blackspot funding.  Council will meet the $100,000 shortfall in order for the project to proceed. 

Update 9.11.2018 - Work commenced on the 5th November 2018 with an anticipated completion date in late March 2019. This project is being funded under the Federal Black Spot program and Council funds. The contractor is aware that Wheelbarrow Road can become busy over the holiday period and has assured council they will attempt to keep delays to a minimum under their traffic management plan, noting that with any road works there will be delays from time to time.  To see an image of the work scope see here. For further information please call 4429 3224.

Nowra

Junction Street/Princes Highway Traffic Signals - 07.11.2018 - The traffic signals at Junction Street were commissioned on Tuesday the 30th October with Council working with the contractor to achieve practical completion. Minor works will continue over the next couple of weeks. Motorist are asked to exercise caution and follow the traffic directions during this time. For more information please call 4429 3224.

O'Keefe Avenue, Roundabout at Berry & Worrigee Streets - an asphalt program will be undertaken commencing Sunday 9 December 2018 and is scheduled for completion by Wednesday 12 December 2018. This work will be NIGHT WORK during the hours of 7pm to 6am.  Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Old Erowal Bay

The Wool Road - 25.10.2018 - The Wool Road at Old Erowal Bay is scheduled for road repair and shoulder widening, works have now commenced. Primer seal is scheduled for 26th October and line marking 2nd November (weather permitting). The project is approaching a major milestone with the road sealing, which is likely to result in further traffic congestion.  Council suggest that commuters leave earlier for important appointments or take a detour.  Peak traffic times can also affect congestion and should be avoided. Shoalhaven City Council apologies for any inconvenience caused to road users and appreciates your patience during this time. For further information please call 4429 3676.

Orient Point

Orient Avenue – Subsoil drainage from Ormonde Cres to Otway St.  For further information please call the Basin District Engineer on 4406 2000.

Shoalhaven Heads

Scott Street, Oval Drive, Davison Drive, Amundsen Avenue, Nimrod Street, Shackleton Street, Discovery Place, Stafford Road, Wharf Road, Ablett Court, Boyd Street, Explorer Boulevard, Golden Hill Avenue, Hanlon Avenue, Hay Avenue, Ingestre Avenue, Jerry Bailey Road, Lovegrove Street, McLay Avenue, River Road, Towers Road, Trentham Road, Wagin Street, David Berry Street, Lloyd Street, Booner Drive - Road resealing was recently completed, weather permitting linemarking will be reinstated by 17 December.    Further information may be obtained by contacting Mr Will Lynch on 4406 2000.

 South Nowra

Albatross Road & Flinders Road Roundabouts – 9.11.2018 – The contractor is working on completing the last section of kerb and gutter and work has commenced on the deep lift asphalt to bring the road to the finished surface level.  Once this is done work will return to the centre concrete island for it to be finished.  When this is completed final line-marking and signage will be done. The contractor is hoping to complete work 30 November 2018. For further information please contact 4429 3409..

Click here to see the plan. Click here to read the Construction Timing Summary.

Flinders Road Upgrade [Norfolk Avenue to Nowra Creek Bridge] – 9-11-2018 – This work has been complete and has entered the 12 months defects liability period.  This means the contractor is obligated during this time to repair any defects or pavement failures at no cost to council.  Council holds securities to ensure that this happens.   For further information please contact 4429 3409.

Norfolk Avenue – A 60m section of industrial road is being extended near the southern end of Cumberland Avenue. For further information please call the Basin District Engineer on 4406 2000.

Sussex Inlet

Jacobs Drive - 04.10.2018 - Streetscape works with minor inconvenience to traffic and parking expected. Paving works are completed, only minor rectifications to be done. Planting works and street furniture installation has commenced, final completion expected at 24th October. For further information please call 4429 3224.

Sussex Inlet Road (Cow Creek Bridge), Jacobs Drive (between Neilson Road and the Cul-de-sac at the end of the Road), River Road (intersection with Ellmoos Ave) - an asphalt program will be undertaken commencing Sunday 2 December 2018 and scheduled for completion by Wednesday 5th December 2018. This work will be NIGHT WORK during the hours of 7pm to 6am.  Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Woollamia

Woollamia Road – Road shoulder reconstruction and sealing is continuing along the residential section of Woollamia Road. For further information please call the Basin District Engineer on 4406 2000.

Worrowing Heights

Naval College Road - 04.10.2018 - The Bridge over Moona Moona Creek on Naval College Road has been replaced. Relocation of the Endeavour ground stay on the southern side has been approved, and the works are expected to be completed by November 2018. Final seal of the road approaches is scheduled for February 2019. For further information please call 4429 3224.

Yerriyong

Wattle Fire Trail (off Yerriyong Road) – Construction of a concrete box culvert across Calymea Creek. For further information please call the Basin District Engineer on 4406 2000.

Back to Top

Upcoming Works

Cambewarra

Far North Collector Road Network - 09.08.2018 - On the 28 June 2018, Council formally accepted a grant from the Federal Government to fund the Design and Construction of the Far North Collector Road. The Council report and Resolution can be found by clicking here. This project has now commenced. For more information on road condition access and information, please contact the Project Manager on (02) 4429 3447.  For full project information please see the Council’s Get Involved Page on the Far North Collector Road Network, available here.

Crookhaven River Bridge Upgrade

The bridge renewal is subject to a detailed engineering design process. Council has currently implemented heavy vehicle restrictions and strict speed limit restrictions on Culburra Road because of the reducing structural integrity of the bridge. Outcomes of the design process should be known towards the end of April 2019. The project is under a Design and Construct tender which will close 22 January 2019 with a likely construction commencement date after the Easter/School Holiday period April 2019.  Tender Details will be provided to the community when further information is available. Council will aim to minimise the impact.  For further information please call 4429 3224.

Huskisson

Huskisson Road - Final sealing of pavements sections are planned for March 2019.  For more information, please contact the Basin District Engineer on 4406 2000.

North Nowra

Greys Beach – Installation of construction piles and pontoons at Greys Beach will be carried out in the coming months, with tenders due to close 26/07/2018. Access to certain areas of the foreshore will be restricted during construction. For further information please call 4429 3224.

Old Erowal Bay

Birrriga Ave – Sealing of the eastern section is planned this financial year. For further information please call the Basin District Engineer on 4406 2000.

Sanctuary Point

Kerry Street, The Park Drive, Heron Avenue, Warrego Drive - Final sealing of pavements sections are planned for March 2019.  For more information, please contact the Basin District Engineer on 4406 2000.

Back to Top

Recently Completed Works

Basin View

The Wool Road, Harris Avenue, Mathie Street - Resealing of Pavement sections.  For further information please call the Basin District Engineer on 4406 2000.

Huskisson/Vincentia

Burrill Street / Elizabeth Drive - 23.07.2018 - The shared user bridge over Moona Moona Creek, and approach pathways, are now completed. The resulting safety improvements for cyclists and pedestrians has been well received. Council appreciates the community’s patience while the project was being undertaken. For further information please contact the Project Manager on 4429 3224.

Hyams Beach

Booderee Avenue, Moonah Road, Hyam Road, Aster Street, Bamboo Avenue, Anemone Avenue - For further information please call the Basin District Engineer on 4406 2000.

Kioloa

Scerri Drive – Kerb and gutter renewal - 47 metres fronting #3 - #7.  For further information, please call 4429 8902.

Nowra

Park Road (# 23 - 25 Kids Korner Combined Occasional Care Centre) – The carpark was be resurfaced  on 23 November.  For further information please call the Engineer - Contracts Officer on 4406 2000.

Sanctuary Point

Edmund Street, Ethel Street, Vost Drive, Boronia Avenue, Fairway Drive, Azalea Avenue, Walmer Avenue, Leumeah Street - Resealing of Pavement sections.  For further information please call the Basin District Engineer on 4406 2000.

Paradise Beach Road and Kingsford Smith Crescent - 22.10.2018 – Construction of a Roundabout and associated pedestrian facilities. The project is now complete with the new roundabout operating. Minor clean-up works remain. Please use caution while adjusting to the changed traffic conditions. For further information please call 4429 3313.

The Wool Road and Larmer Avenue – Repair of damaged concrete paths. For further information please call the Basin District Engineer on 4406 2000.

St Georges Basin

Grange Road, The Wool Road -  For further information please call the Basin District Engineer on 4406 2000.

Sussex Inlet

River Road – The construction of a raised concrete pedestrian threshold will be located approx. 35m south of Chris Creek Bridge is complete.  For further information please call 4429 8902.

Back to Top

Meetings & Agendas

View all agendas and minutes for Council and Committee meetings.
Agendas & Minutes

Newsletter Signup

Signup for our In Your Neighbourhood newsletter and get news direct to your inbox!

© 2018 Shoalhaven City Council
Copyright  |   Privacy  |   Site Map