Road Conditions

For the latest traffic information on the Princes Highway and Moss Vale Road  visit www.livetraffic.com, download the Live Traffic App or call the Transport Management Centre on 132 701.

Road Infrastructure Projects Information


Current Works
Upcoming Works
Recently Completed Works
Understanding Road Repairs


Please note that all quoted completion dates are subject to change due to weather conditions, emergencies or other unforeseen interruptions.

Latest News - Monday 15 April 2019

Current Works

Bendalong

Waratah Street – Stage 2 of the Bendalong Pathway. Approximately 315m of concrete pathway 1.8m wide. Works will commence approx. 50m west of Poplar Street and finish approx. 40m east of Cedar Street. For further information, please call 4429 8902.

Culburra

Plimsoll Place,  Mona Street - Road resealing.  Work is due for completion April 2019. After the reseal is completed, some loose stone will remain on the road surface.  Please drive carefully to minimise loss of tyre traction and stone throwing.  Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Cunjurong Point

York Street – Pavement rehabilitation is scheduled for mid to late April. The work will comprise a new granular base course followed by a bituminous wearing surface. During construction, access to Lake Conjola and the public amenities will be restricted between 7am and 4pm. For more information, please contact the Roads Unit on 4406 2000.

Kangaroo Valley

Jack’s Corner Road, Cullen Crescent - Road resealing.  Work is due for completion April 2019. After the reseal is completed, some loose stone will remain on the road surface.  Please drive carefully to minimise loss of tyre traction and stone throwing.  Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Mollymook

Mitchell Parade – Rehabilitation between Tallwood Ave and Donlan Rd is now complete. The pavement is scheduled for linemarking early April.  For more information, please contact the Roads Unit on 4406 2000.

Mollymook Beach

Blackwater Creek Bridge Mitchell Parade - Abutment protection repair works scheduled for 2 April. For further information call 4429 8902.

Narrawallee

Aries Place – Stormwater drainage upgrade #4 Aries Place. Works will involve the upgrade of the existing drainage system crossing Aries Place. For further information, please call 4429 8902.

Nowra

Junction Street / Princes Highway Traffic Signals - Following the commissioning of the traffic signals, Council is working with the Contractor to achieve Practical Completion.  Minor works will be undertaken in the near future. Motorists are asked to exercise caution and follow the traffic directions during this time. For more information please call 4429 3221.

Orient Point

Orient Avenue, Otranto Avenue, Ormonde Crescent - Rehabilitation of the existing pavement between Ormonde Cres and Otway St has commenced. The work comprises the drain rectification, followed by a granular overlay using fresh roadbase. During the construction Orient Ave will be closed in stages, and short detours will be in place. Residents will have access to their properties, but should consult the ground staff prior to entering the construction zone to mitigate potential accidents and interruptions to construction. For more information, please contact the Roads Unit on 4406 2000.

Sanctuary Point

Larmer Avenue – Rehabilitation works between the Cockrow Creek Bridge and Paradise Beach Rd. The works comprise the removal of the existing seal, remixing and strengthening the existing pavement, placement of a primer seal, followed by an asphalt wearing surface. Finished surface levels and the appropriate compaction have been difficult to achieve in some locations due to weather and soft foundations, hence the need for reworking of the pavement.  Despite the above a Primer Seal was applied to protect the work whilst the rectification plan was fine tuned following detailed compaction testing and level checking.

The road has been reopened to traffic until the rectification works commence. Work is expected to recommence in April and be finished soon after the coming Easter Holidays. The work will be temporarily suspended so as to provide unimpeded traffic flow during the school holidays.  For more information, please contact the Roads Unit on 4406 2000.

Sassafras

Touga and Tolwong Roads – Maintenance grading in April. For more information, please contact the Basin District Engineer on 4406 2000. 

 Sussex Inlet

Jacobs Drive - Construction of two raised threshold pedestrian crossings. The first crossing is being constructed between Neilson Road and River Road and should be complete before the school holidays.  The second crossing is to be started after the school holidays and will be east of River Road.  Traffic Control measures will be in place along Jacobs Drive during construction and will generally involve closing one lane at a time.  For more information, please contact the Basin District Engineer on 4406 2000.

Jacobs Drive - Streetscape works are completed, only minor rectification works remain. For further information please call 4429 3676.

Vincentia

Ann Street – Kerb and Gutter to five properties (South side). For more information, please contact the Basin District Engineer on 4406 2000. 

Worrigee

Beyeri Avenue, Racemosa Ave, Tummell Close, Arthur Street, Robinia Way, Sophia Road, Marsden Close - Road resealing.  Work is due for completion April 2019. After the reseal is completed, some loose stone will remain on the road surface.  Please drive carefully to minimise loss of tyre traction and stone throwing.  Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Worrowing Heights

Naval College Road - Asphalt works have been completed on Naval College Road (at the intersection of Port Jervis Road).  Line marking to be reinstated April 2019 (Weather Permitting).  Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Back to Top

Upcoming Works

Berry

Albert Street - Rehabilitation between Alexandra St and Prince Alfred is scheduled to commence early May 2019. The works comprise the construction of new kerb and gutter where damaged, and the removal/replacement of existing pavement materials and minor changes to traffic conditions can be expected during the construction period. For more information, please contact the Roads Unit on 4406 2000.

Edwards Street – Replacement of the existing timber bridge and pedestrian path with precast concrete culverts. A Design and Construct tender is due to be advertised in early March 2019. Following the engagement of a contractor, a detailed design is to be completed and the culverts procured prior to construction commencing in early August.  Works on site are expected to take 2 months. For more information, please call 4429 3221.

Bomaderry

Bolong Road – New Concrete floor to box culvert near Manildra entrance. For more information, please contact the Basin District Engineer on 4406 2000.

Cambewarra

Far North Collector Road Network - The Far North Collector Road will link Illaroo Road (near the western end of West Cambewarra Road) to Moss Vale Road at Bells Lane in North Nowra. The project has now commenced with preliminary stages including initial land acquisitions, project planning and development, and survey and design. For more information on road condition access and information, please contact the Project Manager on 4429 3447.  For full project information please see the Council’s Get Involved Page on the Far North Collector Road Network, available here.

Crookhaven River Bridge Upgrade

Bridge renewal is subject to a detailed engineering design process.  Council has implemented heavy vehicle restrictions and strict speed limit restrictions on Culburra Road due to the reducing structural integrity of the bridge.

The project is under a Design and Construct tender which closed 22 January 2019. Council staff are currently reviewing tenders. This design process is expected to be complete and approved for construction towards the end of April 2019.

Construction will be scheduled for commencement in June 2019 pending the requirements of design approvals.

Council will aim to minimise the impact to the Community throughout the works. Construction will be staged such that Culburra Road will be open to traffic throughout the works.  For further information please call 4429 3409.

Kings Point

Kings Point Drive – Stormwater drainage repair/replacement of failing stormwater system. For further information, please call 4429 8902.

Little Forest

Coral Tree Lane – Storm water drainage repair/replacement of failing stormwater road crossing. For further information please call 4429 8902.

Tallwood Avenue – Bus shelter relocation and associated pathway works between Jones Avenue & Mitchell Parade. For further information, please call 4429 8902.

Mollymook Beach

Mitchell Parade – Rehabilitation between Clyde St and Donlan Rd is scheduled to commence May 2019. The works comprise the removal of the existing oxidised asphalt, stabilising of in-situ pavement materials and the placement of a new asphalt wearing course, within the main carriageways and the construction of a new concrete roundabout at the Donlan Rd intersection. Minor changes to traffic conditions can be expected, and when the Donlan Rd intersection is closed detours will be in place until the project is complete. For more information, please contact the Roads Unit on 4406 2000.

Morton

Wheelbarrow Rd- Rehabilitation of Wheelbarrow Rd from 3km to 4km west of the Princes Highway is scheduled to commence early May 2019. The works comprise the reshaping and removal of loose materials on the uphill batter cut face, improvements to drainage, minor vegetation management, granular overlay of the existing road pavement course followed by a bituminous wearing surface. During the construction period resident access will be maintained, however the road will be closed to all other through traffic. For more information, please contact the Roads Unit on 4406 2000.

Nowra

Worrigee / Kinghorne Streets – repair works to roundabout. Replacement of brickwork and garden bed. For more information please call the Northern Maintenance Office on 4429 3821.

Sanctuary Point

Waratah Crescent – Stormwater pipeline construction near The Park Drive intersection. For more information, please contact the Basin District Engineer on 4406 2000.

Vincentia

Ann Street – Kerb and Gutter to five properties (South side). For more information, please contact the Basin District Engineer on 4406 2000. 

Elizabeth Drive – Kerb and Gutter from Albion St to Banksia St (East side). For more information, please contact the Basin District Engineer on 4406 2000.

The Wool Road and Naval College Road Roundabout – Widening of the concrete perimeter strip in preparation for planting shrubs. For more information, please contact the Basin District Engineer on 4406 2000.

Back to Top

Recently Completed Works

Bawley Point

Murramarang Road – Culvert installation for the community pathway project. For further information, please call 4429 8902.

Berry

Albert / Prince Alfred Streets – construction of approx. 85m kerb & gutter and maintenance of existing kerb & gutter prior to roadworks in the area. For more information please call the Northern Maintenance Office on 4429 3821.

Berry Mountain

Woodhill Mountain Road – Substantial Road repairs between chainage 3.25km and 4.69km are complete. The road is now open to vehicles, and all traffic conditions returned to normal. Thank you to the residents and general road users for your understanding during construction. For more information, please contact the Roads Unit on 4406 2000.

Burrill Lake

Princes Avenue – Stormwater drainage construction #19 Princess Avenue. For further information, please call 4429 8902.

Callala Beach

Forest Road, Callala Beach Road - Road resealing. Work is due for completion April 2019. After the reseal is completed, some loose stone will remain on the road surface. Please drive carefully to minimize loss of tire traction and stone throwing. Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Cambewarra

Kongoola Avenue ,Tannery Road, Woolway Close - Road resealing. Work is due for completion April 2019. After the reseal is completed, some loose stone will remain on the road surface. Please drive carefully to minimize loss of tire traction and stone throwing. Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Falls Creek

Dowling Street – Pavement reconstruction has been carried out in readiness for sealing. For further information please call the Basin District Engineer on 4406 2000.

Falls Road West - Pavement reconstruction has been carried out in readiness for sealing. For further information please call the Basin District Engineer on 4406 2000.

Falls Road West – Road resealing commencing 18 March 2019. Work is due for completion April 2019. After the reseal is completed, some loose stone will remain on the road surface. Please drive carefully to minimize loss of tire traction and stone throwing. Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Huskisson

Huskisson Road - Road resealing commencing 18 March 2019. Work is due for completion April 2019. After the reseal is completed, some loose stone will remain on the road surface. Please drive carefully to minimize loss of tire traction and stone throwing. Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Little Forest

Coral Tree Lane – Storm water drainage repair/replacement of failing stormwater road crossing. For further information, please call 4429 8902.

Nowra

Berry Street, Bice Road, Dudley Avenue, Greenwell Point Road, Hawthorn Avenue, Junction Street, Kinghorne Street, Osborne Street, Rainford Road, Shepherd Street, Shoalhaven Street, Westborne Drive, Cabbage Tree Lane - Road resealing. Work is due for completion April 2019. After the reseal is completed, some loose stone will remain on the road surface. Please drive carefully to minimize loss of tire traction and stone throwing. Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.Moss Street (Between the Princes Highway and North Street) - Asphalt works have been completed. Line marking to be reinstated by 1 March 2019 (Weather Permitting). Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Lawrence Avenue – extension of the paved pathway connecting to the car park entrance. For more information please call the Northern Maintenance Office on 4429 3821.

Osborne Street – construction of a 1.2m wide footpath along the Eastern side between Worrigee & Plunkett Streets, and various sections on the Western side between Worrigee & Junction Streets and North & Hyam Streets.  For more information please call the Northern Maintenance Office on 4429 3821.

Numbaa

Millbank Rd, Jindy Andy Lane - Road resealing. Work is due for completion by 22 March 2019. After the reseal is completed, some loose stone will remain on the road surface. Please drive carefully to minimize loss of tire traction and stone throwing. Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Old Erowal Bay

Birrriga Avenue – Pavement reconstruction has been carried out in readiness for sealing. For further information please call the Basin District Engineer on 4406 2000.

Sanctuary Point

Heron Avenue, Kerry Street, The Park Drive, Warrego Drive - Road resealing commencing 18 March 2019. Work is due for completion April 2019. After the reseal is completed, some loose stone will remain on the road surface. Please drive carefully to minimize loss of tire traction and stone throwing. Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Sussex Inlet

Anisdale Street, Edgewater Avenue, Ethel Avenue, Lakehaven Drive, Riveria Ave, Goldsmith Road, Mary Street, Matilda Ave, Medlyn Avenue, Pacificana Drive, Ray Street, Ridge Avenue, Wunda Avenue, River Road - Road resealing commencing 18 March 2019. Work is due for completion April 2019. After the reseal is completed, some loose stone will remain on the road surface. Please drive carefully to minimize loss of tire traction and stone throwing. Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

River Road – Pathway repairs. For further information, please call 4429 8902.

Tomerong

Pine Forest Road - Resealing commencing 18 March 2019. Work is due for completion April 2019. After the reseal is completed, some loose stone will remain on the road surface. Please drive carefully to minimize loss of tire traction and stone throwing. Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Worrowing

Birriga Avenue - Road resealing commencing 18 March 2019. Work is due for completion April 2019. After the reseal is completed, some loose stone will remain on the road surface. Please drive carefully to minimize loss of tire traction and stone throwing. Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Yerriyong

Wattle Fire Trail (off Yerriyong Road) – Construction of a concrete box culvert across Calymea Creek. For further information please call the Basin District Engineer on 4406 2000.

Back to Top

Meetings & Agendas

View all agendas and minutes for Council and Committee meetings.
Agendas & Minutes

Newsletter Signup

Signup for our In Your Neighbourhood newsletter and get news direct to your inbox!

© 2019 Shoalhaven City Council
Copyright  |   Privacy  |   Site Map