Road Conditions

For the latest traffic information on the Princes Highway and Moss Vale Road  visit www.livetraffic.com, download the Live Traffic App or call the Transport Management Centre on 132 701.

Road Infrastructure Projects Information


Current Works
Upcoming Works
Recently Completed Works
Understanding Road Repairs


Please note that all quoted completion dates are subject to change due to weather conditions, emergencies or other unforeseen interruptions.

Latest News - Tuesday 19 February 2019

Current Works

Bawley Point

Murramarang Road – Culvert installation for the community pathway project. For further information, please call 4429 8902.

Berry

Victoria Street – Rehabilitation work has been completed between Queen St to George St.  Recent minor works including the installation of traffic signs, new kerb ramps, refuge island and footpath construction is also complete. Formal linemarking is to be installed by external contractors and have advised the linemarking will be completed by the end of the month.  For more information, please contact the Roads Unit on 4406 2000.

Berry Mountain

Woodhill Mountain Road – Rehabilitation works between the new highway overpass and Broughton Vale Rd is now complete. Minor repairs / rework between Bong Bong Rd and Broughton Vale Rd are currently underway. Pavement surfacing and traffic signs are now installed and linemarking scheduled for completion early 2019.  For more information, please contact the Roads Unit on 4406 2000.

Woodhill Mountain Road – Substantial Road repairs between chainage 3.25km and 4.69km from the Queen St Roundabout are scheduled for week 4 March 2019 with an estimated completion date of 29 March 2019. A road closure for through traffic will be in place on working days only, Monday to Friday from 9:00am to 3:00pm, thus allowing for morning and afternoon school bus runs. Additionally, a 20-minute opening between 12:00 and 12:20pm will be provided. Variable message boards will be set up on the approaches to the site to advise road users of the change to traffic conditions.  The Woodhill Mountain Rd pavement width has forced the work to be carried out under a road closure for through traffic as operating the grader and the resultant loose pavement gravel, don’t leave enough room for conventional one lane traffic control measures to be implemented. Council appreciates that the closure is an inconvenience to those residents who live in The Wattamolla, Brogers Creek, Woodhill Mountain and surrounding areas, and has planned a closure timetable to try to balance everyone’s needs. The work site and detour plan is illustrated on the map.  For more information, please contact the Roads Unit on 4406 2000.

Culburra Beach

Prince Edward Avenue - Road repair works are now completed. Final seal was completed Friday 25 January and line marking is scheduled for mid-February.  For further information please call 4429 3409.

Milton

Matron Porter Drive – Shared User Pathway Stage 4, the construction of approximately 700m of concrete pathway 2.5m wide between Sungrove Lane & Garside Road is nearing completion with some minor works remaining.  For further information please call 4429 8902.

Mollymook

Mitchell Parade – Rehabilitation of the northbound lane, approx. 200m in length, between Beach St and Bannister Head Rd is currently underway. The work comprises the replacement of existing pavement materials and is scheduled for completion by the end of the February. For more information, please contact the Roads Unit on 4406 2000.

Mitchell Parade – Rehabilitation between Tallwood Ave and Donlan Rd is currently underway. The work comprises the replacement of existing pavement materials and is scheduled for completion mid March 2019. Minor changes to traffic conditions can be expected up to week commencing 4 March 2019, where the Donlan Rd intersection will closed and detours in place until the project is complete. For more information, please contact the Roads Unit on 4406 2000.

Morton/Woodburn

Wheelbarrow Road  - 1.22 kms of Wheelbarrow Road is scheduled to be bitumen sealed, widened with new shoulders, signage and guideposts installed. Work has commenced with an anticipated completion date in late March 2019. To see an image of the work scope see here.

Work is progressing however, has been delayed by heavy rains. The southern section of the road is under construction and it is planned to be sealed late February 2019.  The contractor will then complete the northern part.  Additional culverts have been constructed to minimise storm damage and road-side scour.  For further information please call 4429 3409.

Nowra

Junction Street / Princes Highway Traffic Signals - Following the commissioning of the traffic signals, Council is working with the Contractor to achieve Practical Completion.  Minor works will be undertaken in the near future. Motorists are asked to exercise caution and follow the traffic directions during this time. For more information please call 4429 3221.

Moss Street (Between the Princes Highway and North Street) - Asphalt works have been completed. Line marking to be reinstated by 28 February 2019 (Weather Permitting). Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Osborne Street – construction of a 1.2m wide footpath along the Eastern side between Worrigee & Plunket Streets, and various sections on the Western side between Worrigee & Junction Streets and North & Hyam Streets. For more information please call the Northern Maintenance Office on 4429 3821.

Old Erowal Bay

Birrriga Avenue – Pavement reconstruction has been carried out in readiness for sealing in March 2019. For further information please call the Basin District Engineer on 4406 2000.

The Wool Road - The road repair and widening is now complete, only minor rectification remaining. These works will take place under traffic control in mid-February 2019, weather permitting.  Speed limits and traffic controls have now been removed. For further information please call 4429 3676.

 South Nowra

Albatross Road & Flinders Road Roundabouts – All roadworks have been completed. Remaining work is line-marking, signage and landscaping.  The contractor is hoping to complete work by the end of February. For further information please contact 4429 3409.

Click here to see the plan. Click here to read the Construction Timing Summary.

Norfolk Avenue – A 60m section of industrial road is being extended near the southern end of Cumberland Avenue. For further information please call the Basin District Engineer on 4406 2000.

Sussex Inlet

Jacobs Drive - Streetscape works are completed, only minor rectification works remain. For further information please call 4429 3676.

Worrowing Heights

Naval College Road - The Bridge over Moona Moona Creek has been replaced. Final road sealing works and permanent line marking are scheduled for mid-February 2019. Speed limits remain in place until works are complete.  For further information please call 4429 3676.

Yerriyong

Wattle Fire Trail (off Yerriyong Road) – Construction of a concrete box culvert across Calymea Creek. For further information please call the Basin District Engineer on 4406 2000.

Back to Top

Upcoming Works

Berry

Edwards Street – Replacement of the existing timber bridge and pedestrian path with precast concrete culverts. A Design and Construct tender is due to be advertised in early March 2019. Following the engagement of a contractor, a detailed design is to be completed and the culverts procured prior to construction commencing in early August.  Works on site are expected to take 2 months. For more information, please call 4429 3221.

Bomaderry

Bolong Road – New Concrete floor to box culvert near Manildra entrance. For more information, please contact the Basin District Engineer on 4406 2000.

Burrill Lake

Princes Avenue – Stormwater drainage construction #19 Princess Avenue. For further information, please call 4429 8902.

Callala Beach

Forest Road, Callala Beach Road - Road resealing commencing 25 February 2019.  Work is due for completion by 1 March 2019. After the reseal is completed, some loose stone will remain on the road surface.  Please drive carefully to minimise loss of tyre traction and stone throwing.  Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Cambewarra

Kongoola Avenue ,Tannery Road, Woolway Close - Road resealing commencing 25 February 2019.  Work is due for completion by 1 March 2019. After the reseal is completed, some loose stone will remain on the road surface.  Please drive carefully to minimise loss of tyre traction and stone throwing.  Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Cambewarra

Far North Collector Road Network - The Far North Collector Road will link Illaroo Road (near the western end of West Cambewarra Road) to Moss Vale Road at Bells Lane in North Nowra. The project has now commenced with preliminary stages including initial land acquisitions, project planning and development, and survey and design. For more information on road condition access and information, please contact the Project Manager on 4429 3447.  For full project information please see the Council’s Get Involved Page on the Far North Collector Road Network, available here.

Crookhaven River Bridge Upgrade

Bridge renewal is subject to a detailed engineering design process.  Council has implemented heavy vehicle restrictions and strict speed limit restrictions on Culburra Road due to the reducing structural integrity of the bridge.

The project is under a Design and Construct tender which will close 22 January 2019. Council staff are currently reviewing tenders. This design process is expected to be complete and approved for construction towards the end of April 2019.

Construction will be scheduled for commencement in May 2019 pending logistical requirements of approved design.

Council will aim to minimise the impact to the Community throughout the works. Construction will be staged such that Culburra Road will be open to traffic throughout the works.  For further information please call 4429 3409.

Culburra

Plimsoll Place,  Mona Street - Road resealing commencing 25 February 2019.  Work is due for completion by 1 March 2019. After the reseal is completed, some loose stone will remain on the road surface.  Please drive carefully to minimise loss of tyre traction and stone throwing.  Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Falls Creek

Dowling Street - Pavement reconstruction and sealing. For more information, please contact the Basin District Engineer on 4406 2000.

Falls Road West – Pavement reconstruction and sealing. For more information, please contact the Basin District Engineer on 4406 2000.

Huskisson

Huskisson Road - Final sealing of patched pavements sections are planned for March 2019.  For more information, please contact the Basin District Engineer on 4406 2000.

Kangaroo Valley

Jack’s Corner Road, Cullen Crescent - Road resealing commencing 25 February 2019.  Work is due for completion by 1 March 2019. After the reseal is completed, some loose stone will remain on the road surface.  Please drive carefully to minimise loss of tyre traction and stone throwing.  Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Kings Point

Kings Point Drive – Stormwater drainage repair/replacement of failing stormwater system. For further information, please call 4429 8902.

Little Forest

Coral Tree Lane – Storm water drainage repair/replacement of failing stormwater road crossing. For further information please call 4429 8902.

Mollymook Beach

Tallwood Avenue – Bus shelter relocation and associated pathway works between Jones Avenue & Mitchell Parade. For further information, please call 4429 8902.

Naval College Road

As part of Council’s ongoing commitment to preserving and enhancing its road pavement assets, an asphalt program will be undertaken on Naval College Road (at the intersection of Port Jervis Road). Commencing Thursday 21 February 2019, Weather permitting works will be completed in by 22 February 2019.

Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000

Nowra

Berry Street, Bice Road, Dudley Avenue, Greenwell Point Road, Hawthorn Avenue, Junction Street, Kinghorne Street, Osborne Street, Rainford Road, Shepherd Street, Shoalhaven Street, Westborne Drive, Cabbage Tree Lane - Road resealing commencing 25 February 2019.  Work is due for completion by 1 March 2019. After the reseal is completed, some loose stone will remain on the road surface.  Please drive carefully to minimise loss of tyre traction and stone throwing.  Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Numbaa

Millbank Rd, Jindy Andy Lane - Road resealing commencing 25 February 2019.  Work is due for completion by 1 March 2019. After the reseal is completed, some loose stone will remain on the road surface.  Please drive carefully to minimise loss of tyre traction and stone throwing.  Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Orient Point

Orient Avenue, Otranto Avenue, Ormonde Crescent - Rehabilitation is scheduled to commence around mid March 2019. Minor changes to traffic conditions can be expected during the construction period. For more information, please contact the Roads Unit on 4406 2000.

Sanctuary Point

Kerry Street, The Park Drive, Heron Avenue, Warrego Drive - Final sealing of pavements sections are planned for March 2019.  For more information, please contact the Basin District Engineer on 4406 2000.

Vincentia

 Elizabeth Drive – Kerb and Gutter from Albion St to Banksia St (East side). For more information, please contact the Basin District Engineer on 4406 2000.

The Wool Road and Naval College Road Roundabout – Widening of the concrete perimeter strip in preparation for planting shrubs. For more information, please contact the Basin District Engineer on 4406 2000.

Worrigee

Beyeri Avenue, Racemosa Ave, Tummell Close, Arthur Street, Robinia Way, Sophia Road, Marsden Close - Road resealing commencing 25 February 2019.  Work is due for completion by 1 March 2019. After the reseal is completed, some loose stone will remain on the road surface.  Please drive carefully to minimise loss of tyre traction and stone throwing.  Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000.

Back to Top

Recently Completed Works

Bawley Point

Bawley Point Road, Islander Avenue, Kywong Avenue, Lurnea Avenue, Malibu Drive, Marloo Avenue, Murilla Avenue, Northaven Avenue, Sunseeker Drive, Surf Tide Avenue, Tingira Drive – Road Resealing has been completed. Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000

Bendalong

Maple Street, Cherry Street, Red Point Road, Willow Street, Jacaranda Avenue, Elm Street, Holly Street - Road Resealing has been completed. Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000

Kioloa

Murramarang Road – Rehabilitation work has now been completed between Scerri Drive to Merry Beach Road. For more information, please call 4429-8902.

Manyana

Alaska Street, The Barbican, The Lookout, The Pannicle - Road Resealing has been completed. Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000

Milton

Croobyar Road - Road Resealing has been completed. Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000

Ulladulla

Burrill Street (South) - Road Resealing has been completed. Further information may be obtained by contacting the Engineer - Contracts Officer on 4406 2000

Back to Top

Meetings & Agendas

View all agendas and minutes for Council and Committee meetings.
Agendas & Minutes

Newsletter Signup

Signup for our In Your Neighbourhood newsletter and get news direct to your inbox!

© 2019 Shoalhaven City Council
Copyright  |   Privacy  |   Site Map