Moss Vale Road Urban Release Area - Water Infrastructure

The Moss Vale Road Urban Release Area (URA) is a regionally significant residential development located between Bomaderry and Cambewarra village.

The new water pumping station as viewed from the street.

The latest

Package 1, 2 & 4 works are now operational.

For updates and upcoming works on Package 3: Stage 2 Water Main Works, see ‘Package 3’ under ‘About the packages of works'.

About the project

The current projected development yield is 3,400 residential lots. In order to supply adequate future servicing to the Urban Release Area (URA), Shoalhaven Water progressed detailed designs for the water and wastewater infrastructure, with construction of the works commenced in 2021.

Progress so far

  • Project approval – 2020
  • Award of design consultants – 2020
  • Stage 1 Water Main Lead-in Works placed in operation December 2021
  • Overall water detailed design completion – 2022
  • Stage 2 Illaroo Road Water Pumping Station Upgrades placed in operation April 2024
  • Stage 4 New 3.5ML Water Reservoir placed in operation July 2024

About the packages of works

Package 1 - Stage 1 water main lead-in work

Package 1 involved the extension of the existing Cambewarra water main network along Main Road and Moss Vale Road, to the Moss Vale Road URA.

Progress so far

  • Package 1 works completed in 2021.

Package 2: Illaroo Road water pumping station upgrade

Package 2 involved the construction of a new upgraded water pumping station.

Progress so far

  • Package 2 works were placed in operation April 2024.
  • A separate landscaping package of works will be undertaken by Council at a later date.

Package 3: Stage 2 water mains

Package 3 involves the construction of new rising mains connecting the Cambewarra, Badagarang and Bomaderry water networks.

Progress so far

  • Watermains have now been installed within Cambewarra Village along Reservoir Lane, Faulks Place, Main Rd & Hockeys Lane with testing of these watermains continuing, with most lines now passing their associated pressure testing.
  • A fault has been detected within a section of the main installed at the intersection of Main Rd / Goorama Dr. Initial investigations of the fault appears to indicate that the damage to the main could be malicious and Council is working with our Contractors to further investigate, resolve and make good.
  • Watermains have now been installed within Badagarang along Moss Vale Road between Lancaster Drive and Bannada Way with testing of these watermains continuing.
  • Works to rectify the defective pipeline along Main road are now complete. The roads affected by the works are now reinstated and all road networks within Cambewarra are now returned to pre-construction conditions.

Upcoming works

  • Remaining watermain to be installed between Bannada Way Badagarang and 25 Moss Vale Road Bomaderry
  • Affected areas within the road reserve are continuing to be reinstate back to pre-construction conditions.

Package 4: New water reservoir

Package 4 involved the construction of a new 3.5ML water reservoir on the existing Cambewarra Reservoir Site at Reservoir Lane.

Progress so far

  • Package 4 works were placed into operation July 2024.

If you have any questions about the above works, please contact Project Manager Robert Greig via email at robert.greig@shoalhaven.nsw.gov.au.

For more information, including the detailed stages, visit the Planning for Growth in Nowra - Bomaderry Get Involved web page.