Below: Site 1 landslip repaired 21 May 2024 and repair works near completion 7 March 2024
Below: Site 2 landslip repaired 21 May 2024 and repair works near completion 7March 2024
Below: Site 3 landslip repaired 21 May 2024 and repair works near completion 7 March 2024
Below: Site 4 landslip repaired 21 May 2024 and repair works near completion 7 March 2024
Below: Site 5 landslip repaired 21 May 2024
Below: Site 5 new design elements needed as adverse ground conditions slow works 7 March 2024
25/6/2024 - Announcement - Contraflow traffic conditions while line marking is underway Wednesday 26 and Thursday 27 June 2024. When line marking is complete traffic control will be removed and Give way signs will control traffic at the single lane point. Council appreciates your patience during completion works.
8/5/2024 - Announcement - Nightworks are cancelled for the rest of this week due to the ongoing heavy rainfall. Nightworks are planned to start again from 9pm Sunday night 12 May 2024, weather permitting. Find details under - About the works. See Related Documents for updated 3-week Lookahead Program 7 May 2024. Council appreciates your patience as major landslip and road repair works near completion.
17/4/2024 - Announcement: Road open Anzac Day Thursday 25 April 2024. Spray seal works are planned Wednesday 17 April 2024 at Site 2 and Site 3, weather permitting. Following the recent natural disaster 7 April 2024 (AGRN1119) severe weather and flooding event, night closures and daytime contraflow are ongoing at Site 4 to 1 May 2024. Find details under - About the works.
10/4/2024 - Temporary Closure: Due to impacts of the 7 April 2024 natural disaster (AGRN1119) storm event closures are extended out a few days. Night closures and daytime contraflow traffic conditions are ongoing at Site 4 to Monday 29 April 2024. Find details under - About the works. Council appreciates your patience as major landslip and road repair works near completion.
3/4/2024 - Announcement: Major landslip repair works are near completion. Repair works are scheduled to be completed at Site 5 - near rural address 356, Friday 12 April and at Site 4 - rural address 610, Saturday 27 April 2024, weather permitting. Remaining spray seal works will be carried out under contraflow traffic conditions.
12/3/2024 - Announcement: Works halt for Easter break.Repair works will shut down for the Easter break from 6am Thursday 28 March through to Monday 1 April 2024. Good news: Contractor Symal has advised a revised completion date of May 2024, weather permitting.
27/2/2024 - Announcement: Works ahead of schedule. Contractor Symal has advised works at Site 4 are progressing ahead of schedule with an anticipated completion date of 26 July 2024. Extra equipment and resources have been mobilised to advance completion of repair works. For details see media release 16 February 2024, under About the works.
Contractor Symal released revised construction program. Find the updated three-week Lookahead Program 27 February 2024 under Related Documents. Repair works and road closures at each site are also detailed under 'About the works'.
20/2/2024 - Announcement: Contractor Symal has advised works at Site 4 near rural address 610 are progressing ahead of schedule. The expected completion date is now 26 July (no longer 30 August) 2024. Night closures are ongoing.
From 2/1/7/2024 to 19/2/2024 – The updated three-week Lookahead program was released each week by contractor, Symal, and published on this page weekly under ‘Related Documents’. Repair works and road closures were also detailed weekly for all sites under ‘About the works’.
Repair works progressing steadily
Above: Site 4 landslip repairs progressing well February 2024.
Above: Site 4 in progress October 2023.
Above: Site 3 repair works are well underway.
Above: Site 1 landslip repair works nearing completion.