30/04/2024 - Works are complete pending minor restoration and removal of site compound from site.
04/04/2024 - Raised pedestrian crossing is complete. Shoulder asphalt is complete. Construction of remaining pram ramps and footpath at the intersection is in progress.
06/03/2024 - Kerb & gutter has been constructed. Footpath works continuing.
20/02/2024 - Kerb & Gutter and footpath construction in progress.
January 2024 Update - Works on site expected to commence late Feb / early March 2024.
December 2023 Update - The contract for these works has been awarded. Works are expected to commence on site late February 2024.
01/11/2023 - Council has submitted a cost variation for this portion of the Ulladulla High School Pedestrian Safety Improvements and is awaiting the outcome.
20/09/2023 - Council has submitted a cost variation for this portion of the Ulladulla High School Pedestrian Safety Improvements and is awaiting the outcome.
18/08/2023 - Council has submitted a cost variation for this portion of the Ulladulla High School Pedestrian Safety Improvements and is awaiting the outcome.
01/08/2023 - Council is proceeding into negotiations with the selected tenderer for the works.
05/07/2023 - Tenders for construction are being evaluated.